we’re delivering 3 major road projects
The 6.5km North East Link tunnels from Watsonia to Bulleen will fix the missing link in our city’s freeway network
take 15,000 trucks off local roads a day and reduce travel times by up to 35 minutes
Upgrades to the Eastern Freeway and M80 Ring Road will include new lanes
smart technology and a seamless connection to the North East Link tunnels
You need to enable javascript to view latest disruptions
Return to the North East Link homepage
Receive regular updates about North East Link
Work on North East Link is powering ahead with tunnelling now underway after launching both Tunnel Boring Machines (TBMs) in Watsonia
With the acoustic shed at Winsor Reserve and all the other temporary tunnelling infrastructure now complete and both TBMs launched
we are getting on with the job of building the 6.5km twin tunnels to Bulleen
We will now be working for more hours of the day and night
and working continuously in some locations to keep these critical tunnelling activities progressing
We will continue to work closely with the local community to inform you of upcoming works. If you feel you are experiencing excessive impacts from construction, we encourage you to contact the project team on 1800 105 105
we are now getting on with continuous work at the Lower Plenty Road interchange and construction of the ventilation building in Yallambie
The first batch of our concrete segments for the tunnel walls have arrived with 44,000 to be supplied from LS Precast in Benalla throughout the tunnelling process
The enclosed conveyor belt is now finished and operating
taking the dirt and rock from the tunnels over Greensborough Road and into the acoustic shed at Winsor Reserve
It is then loaded into trucks and moved off site to our EPA approved facilities
Crews have also installed a massive mural on the west and north walls of the acoustic shed
natural landscape that depicts a visual story from morning to night
which features local animals that come out at these different times
Construction on the northern ventilation building has started with work on the foundations underway
The ventilation tunnel that will connect this building to the main tunnel entrance is over half way completed
Work to build the Lower Plenty Road interchange has been progressing well with excavation of the main box ramping up while the team continue building foundations deep underground
These works will allow us to build the ramps that will take road users in and out of the tunnels
our focus shifts to upgrading local roads and park lands
We’ve already started widening Lower Plenty Road at Greensborough Road with more stages to come
including the installation of the Iuk (eel) pedestrian and cycle bridge which will connect the Rivergum Walk Trail to the upgraded Borlase Reserve
We've also started site investigations around the Silk Street pedestrian bridge as we prepare to upgrade it before the project is complete
The pedestrian bridge will be upgraded with improved functionality and height
giving the bridge a modern look that will enable large vehicles to travel under it along Lower Plenty Road
We’ll also begin building the new tree-lined Greensborough Road boulevard
which will include creating a service road along sections of the boulevard to allow locals safer access to and from their homes
Work will continue at our Lower Plenty Road interchange site to build the new tunnel entry and exit ramps and prepare for the TBMs to travel through the area next year
we’ve moved the Watsonia Road and Greensborough Highway intersection to create the space needed to build the Watsonia Road bridge and connection to North East Link
We’ll be working regularly along Greensborough Highway near Watsonia Road. To find out more and plan ahead, visit our Disruptions page
In partnership with Women in Construction and the Civil Contractors Federation
North East Link is providing Victorians the opportunity to undertake a Certificate III Civil Construction Traineeship paving the way for women to thrive in the construction industry
The 18-month program blends trainer-led online sessions
on-site practical observation and time in a classroom
This flexible structure allows participants to manage their training alongside work commitments
This program provides the opportunity for women to build on their existing skill set and forge a pathway in the construction industry. Find out more about employment opportunities on the project via northeastlink.vic.gov.au/jobs
We're working closely with the local community to manage the impact of works
All works are carefully planned and managed to make sure residents can continue to enjoy where they live and local businesses can continue to operate
we use lights to provide safe working conditions
We limit the light impacts on residential areas by facing lights towards work areas and away from homes as much as possible
We also use shields to minimise light spill into surrounding areas
We try to avoid creating dust during construction
we will limit its impact on the environment by:
Strict controls have been put in place to make sure construction noise is well managed and complies with the Environment Protection Authority (EPA) Victoria guidelines
If you feel you are experiencing excessive impacts from construction, contact the project team on 1800 105 105 or visit our Community Hub at 17 Watsonia Road
Watsonia between 9am and 5pm Monday to Friday
North East Link has partnered with Yurringa Energy – an Aboriginal owned renewable energy provider that will supply green power to the project
This means our Tunnel Boring Machines digging the 6.5km twin lane tunnels will be powered by 100% renewable energy
Yurringa Energy is creating employment opportunities for First Nations Peoples
as well as providing training and development opportunities to support career growth
For languages other than English please call 9209 0147
Please contact us if you would like this information in an accessible format. If you need assistance due to a hearing or speech impairment, visit relayservice.gov.au
Artist’s impression of M80 Ring Road and Macorna Street walking and cycling bridge
The completed M80 Ring Road will take 19,000 cars and trucks a day off Greensborough Road with through traffic passing under Grimshaw Street
Elder Street and Watsonia Road – giving local roads back to local people
New free-flowing interchanges at the M80 Ring Road and Grimshaw Street will ease congestion and slash travel times
with dedicated lanes for local trips and express lanes to the North East Link tunnels
More than 10km of new and upgraded walking and cycling paths and better connections to Watsonia Station and shops will make it safer and easier to move about local suburbs
The project is planned to open at the same time as the North East Link tunnels from Watsonia to Bulleen and the Eastern Freeway Upgrades from Hoddle Street to Springvale Road
Use the map to explore the project design for the M80 Ring Road Completion
For more information, read the project design fact sheet or the M80 Ring Road Completion Urban Design and Landscape Plan
Receive updates and disruption notifications from the M80 Ring Road Completion
delivering new lanes through to Plenty Road and a seamless connection to the North East Link tunnels – taking 19,000 cars and trucks a day off Greensborough Road and giving local roads back to local people
We’ll also build new interchanges at the M80 Ring Road and Grimshaw Street
more than 10 kilometres of new and upgraded walking and cycling paths
better local connections to Watsonia Station and shops
and new noise walls to meet a tougher traffic noise standard of 63 decibels during the day
As we build the M80 Ring Road Completion, there will be major changes to how you move about by road and rail. To stay up to date on works in your area, sign up for updates at bigbuild.vic.gov.au/roads-subscribe
We’re connecting the M80 Ring Road to the North East Link tunnels – taking traffic and trucks off local roads
new landscaped bridges and new and upgraded walking and cycling paths will also make it easier for locals to get to schools
public transport and improved green spaces
Taking traffic and trucks off local roads and improving local trips
Connections for local trips and new express lanes for North East Link
Both bridges will have wide walking and cycling paths along both sides
green landscaping and fewer cars and trucks on Greensborough Road for easier trips to the station and shops
We've also started planting trees early in local parks
Dedicated lanes will take through traffic and trucks off Greensborough Road and under Grimshaw Street
Elder Street and Watsonia Road – returning local roads to local people
The M80 Ring Road Completion will be timed to open around the same time as the North East Link tunnels from Watsonia to Bulleen and Eastern Freeway Upgrades
Your feedback at work More than 15,900 pieces of community feedback since 2017 have helped develop the design for the M80 Ring Road Completion
construction compounds are needed at AK Lines Reserve and Gabonia Avenue Reserve
we’ve reduced the size of the compounds and will be returning improved spaces at the end of construction
New multi-million dollar facilities have also been built at Binnak Park and Greensborough College to support local players during construction
Winsor Reserve will be used to support tunnelling from Watsonia to Bulleen
The acoustic shed is nearing completion and will be around 140m long
enclosed conveyor belt over Greensborough Road
with the 35-metre bridge structure over Greensborough Road now installed
When the tunnel boring machines (TBMs) start tunnelling from mid-2024
the dirt and rock that is removed will be carried on this belt from the launch site at Watsonia over Greensborough Road and into the acoustic shed at Winsor Reserve
The dirt will then be safely loaded onto covered trucks and taken off-site
Truck wheel wash stations will be installed on site at Winsor Reserve to reduce dirt and rock making its way on roads
You’ll see an increase in truck movements once tunnelling starts to keep pace with the TBMs digging underground
we’ve installed traffic lights on Greensborough Road
ensuring trucks exiting Winsor Reserve have minimal impact on traffic flow
The playground and walking path at the back of Winsor Reserve near Tuckfield Court will remain open for local use
the reserve will be reinstated and returned to the community for public use
Read our fact sheet Tunnel construction in Watsonia and Macleod
Read our construction update Construction ramps up from Yallambie through Watsonia
with the first tunnel boring machine (TBM) now digging the 6.5 kilometre road tunnels between Watsonia and Bulleen
It’s the first of two massive machines that will help dig the twin tunnels that will take 15,000 trucks off local roads and save drivers up to 35 minutes
and 4000 tonnes - among the biggest in the southern hemisphere
In keeping with tradition, TBMs are named before they start work, and the North East Link TBMs have been named Zelda and Gillian after 2 groundbreaking local women
The late West Heidelberg resident Zelda D’Aprano AO (1928-2018) was a renowned activist
notably chaining herself to a building when an equal pay case was dismissed in 1969 and establishing the Women’s Action Committee
She was a key player in a long campaign by many remarkable women working toward closing the gender pay gap
Dr Gillian Opie is a neonatal paediatrician at the Mercy Hospital for Women in Heidelberg
Dr Opie founded Australia’s first breast milk bank more than 10 years ago
providing sick and premature babies in Melbourne’s neonatal intensive care units (NICU) with safe
TBM Zelda and TBM Gillian will dig approximately 10 metres per day and up to 45 metres underground
building the tunnels that will pass traffic under instead of through local suburbs
The tunnels will be built using 100% renewable electricity
and dirt and rock from the tunnels will be re-used across North East Link and other transport sites where possible with a significant amount of dirt also helping rehabilitate a former quarry at Point Wilson and the former Orica site in Deer Park
the TBMs will install tunnel walls made of approximately 44,000 individual concrete segments that have been made locally in Benalla
with the tunnels opening to traffic in 2028
Stay updated about North East Link with the key announcements and milestones
We’re fixing the missing link between the M80 Ring Road and an upgraded Eastern Freeway – reducing travel times by up to 35 minutes and taking 15,000 trucks off local roads a day
We’ve listened to what people had to say through the Environment Effects Statement (EES) process. In late 2021 we released a project design with longer 6.5km tunnels to Watsonia, simpler interchanges and 50 MCGs of open space across the entire North East Link Program
a team of some of the best builders in Australia and around the world
to build the North East Link Tunnels from Watsonia to Bulleen
we’re exhibiting an Urban Design and Landscape Plan to ask the community what they think of the look and feel of what’s planned for their area
bike and walking paths and improvements to local roads
Subscribe to our e-newsletter
The North East Link Tunnels will take traffic and trucks under instead of through our suburbs and give local roads back to local people
Longer tunnels and a simpler Lower Plenty Road interchange have created more space for new parklands
better walking and cycling paths and to change Greensborough Road into a tree-lined boulevard
See the map on the fact sheet for more details
In response to community feedback we’ve extended the North East Link Tunnels to Watsonia by tunnelling an extra 1.9km using tunnel boring machines (TBMs) – keeping more works underground
If you live in the local area and want to use North East Link it’s now easier
Ramps in Watsonia will connect you to the M80 Ring Road
Ramps in Yallambie will connect you to the Eastern Freeway
Greensborough Road will be a better road for local trips and to live on
We’re using space created by the longer tunnels to:
We’re also delivering the better east-west access people asked for with:
6 new and upgraded intersections and crossings will make Greensborough Road safer and easier to use
The simpler Lower Plenty Road interchange has created 5 MCGs of new parklands along Banyule Creek
including a major expansion of Borlase Reserve to the north with space to:
The design for the ventilation structure has been inspired by traditional Wurundjeri eel traps and surrounded by new trees and plants
Solar panels on the sides will help power the tunnels below
Yallambie and Rosanna will deliver 3.4km of new and upgraded walking and cycling paths including:
trees will need to be removed while we’re working at the surface
This will help make space to launch and operate the tunnel boring machines
build the Lower Plenty Road interchange and the new Greensborough Road boulevard
at least 2 will be planted including extensive planting along the new Greensborough Road boulevard
at the new Borlase Reserve parklands and to revitalise Banyule Creek where land used for construction will be returned to the local community
While we’re refining the design through the Urban Design and Landscape Plan (UDLP)
you’ll see us out and about getting ready for major tunnelling works to begin later this year
We’re working on the best route for the tunnel boring machines to take beneath the Yarra River and parklands and will be out talking to residents who will have the tunnel near them later this year
Visit our website for more information about works in your area and to sign up for regular updates
The Urban Design and Landscape Plan for the North East Link Tunnels is on exhibition now
The UDLP has detailed maps and drawings of the project design and an explanation of how it meets strict requirements in place for North East Link
Making a submission is your opportunity to have a say on local elements for your area including new parklands
walking and cycling paths and improvements to local roads
We’ll be using what we hear to finalise the UDLP before submitting it to the Minister for Planning later this year for approval and getting major construction underway
You can find out more about the UDLP and see a copy online from Wednesday 11 May to Tuesday 31 May 2022 at Engage Victoria or visit a display and talk with our team at:
17 Watsonia Road, Watsonia
191 Bulleen Road, Bulleen
You can also view the UDLP at local council offices and libraries. To find a location near you visit Engage Victoria
Make your submission online at Engage Victoria by 5pm
If you need help accessing the UDLP, or to make a submission, please contact us on 1800 105 105 or at community@northeastlink.vic.gov.au
This information is current at the time of publication
Please visit our website for the latest updates
Fixing the missing link between the M80 Ring Road and an upgraded Eastern Freeway
The North East Link Tunnels will slash travel times by up to 35 minutes and take 15,000 trucks off local roads a day
We’ve listened to what people had to say and are building longer 6.5km tunnels to Watsonia
simpler interchanges and 50 MCGs of open space across the entire North East Link Program
This includes Victoria's longest road tunnels
interchanges at Lower Plenty Road and Manningham Road
Visit the project team at the Watsonia Hub, 17 Watsonia Road. Find us on Google maps
The North East Link Tunnels will take traffic and trucks under
our suburbs and give local roads back to local people
better walking and cycling paths and transforming Greensborough Road into a tree-lined boulevard
In response to community feedback through the project's planning approvals
we're building longer tunnels to Watsonia – tunnelling an extra 1.9km using tunnel boring machines (TBMs) to keep more works underground
If you live in the local area and want to use North East Link
ramps in Watsonia will connect you to the M80 Ring Road
As part of the Lower Plenty Road interchange design we're building 5 MCGs of new parklands along Banyule Creek
The design for the ventilation structure is inspired by traditional Wurundjeri eel traps and surrounded by new trees and plants
See the map on the factsheet (PDF, 2.2 MB) for more details
For every tree removed to build North East Link
at least two will be planted including extensive planting along the new Greensborough Road boulevard
More than 15,900 pieces of community feedback since 2017
including over 870 submissions on the project’s Environment Effects Statement
have helped develop the design for North East Link
In 2022 we exhibited an Urban Design and Landscape Plan for the North East Link Tunnels and asked local people to provide feedback on the design for their local area
In response to feedback received we’re:
Find more information about what we heard in submissions and the changes made in response
While most of the work to build the North East Link Tunnels will happen deep underground
major works are needed at the surface to launch and operate the tunnel boring machines (TBMs)
tunnel ventilation structure and new Greensborough Road boulevard
The TBMs will be launched and operated from the start of the tunnel in Watsonia
with a supporting compound at Winsor Reserve in Macleod to manage the dirt excavated
The Lower Plenty Road interchange ramps will be built using a method called cut and cover
A deep area will be excavated to build the tunnel and connecting ramps
We'll be keeping the local community up to date on works in your area as we build the North East Link Tunnels
The North East Link Tunnels are just one part of the biggest ever investment in Melbourne's north east
We're also completing the Ring Road in Greensborough
building Melbourne's first dedicated busway and the North East Trail – more than 34km of new and upgraded bike and walking paths
This massive program of works is being carefully planned so the whole project can open around the same time in 2027/2028 - bringing all the pieces of North East Link together
See the project timeline on the factsheet (PDF, 2.2 MB) for more details
This information is current at the time of publication, however changes may occur. Please visit our website for the latest updates
The Urban Design and Landscape Plan (UDLP) for the M80 Ring Road Completion from Greensborough to Watsonia has been approved
In response to community feedback received through the project’s Environment Effects Statement
the UDLP exhibited for comment included improved interchange designs at the M80 Ring Road and Grimshaw Street
better locations for walking and cycling bridges at Macorna Street and Nell Street
a wider landscaped bridge at Watsonia Road and a new landscaped bridge at Elder Street
While the plan was on exhibition in October 2023
it was viewed online more than 13,600 times
Over 670 people visited our Watsonia Community Hub to speak with our team
and just over 475 submissions were received
In response to submissions received the final UDLP approved by the Minister for Planning in September 2024
includes further improvements to the design including:
Thank you to everyone who took an interest in the UDLP online
came to an information session or gave us your feedback
You can read more about what we heard, and changes made to the UDLP in the Community Consultation Report - PDF, 5.3 MB
See the approved UDLP
We’re planning to move one set of transmission towers at Watsonia to the other side of Greensborough Road
Moving the towers from the train station car park to the power line easement will:
the new transmission towers would be about 80m away from their original location
The relocation of the transmission towers has been informed by comprehensive technical studies and consultation with AusNet Services
the owner and operator of the Victorian electricity transmission network
We investigated whether it’s possible to move the power lines underground but found homes would be required
two large transition towers that move the power lines from above ground to below ground would need to be built and surrounded by safety compounds
The existing power line easement is only 50-55m wide
As well as requiring homes along the power line easement
the compounds would permanently take up open space and may have a greater visual impact than keeping the lines above ground
Moving lines underground would require homes
public space and may have greater visual impacts than keeping the lines above ground
This set of towers is needed to keep the tension in the power lines tight and at a safe height
Removing the towers would not comply with current regulations and introduce significant safety risks to the public
Work to move the towers is expected to start in early 2020 after we are expected to receive planning approvals for the North East Link Program
Moving the towers should take around 6 months
intensive bursts of around a few days at a time and local residents would be advised before works start
We expect to be able to move the transmission towers without businesses or homes losing power
Work to move the towers would be staged in a way that isolates only the lines being worked on
This would keep other power lines live so power can stay on in the local area and across the broader network
The proposed project design for this area includes upgrades to paths along the power line easement to make walking and riding around Watsonia safer and easier
Some of the existing paths along the easement would be moved so they better connect to:
a new green bridge at Elder Street for trips to the station and shops
a new path next to Greensborough Road all the way between River Gum Walk at Lower Plenty Road and the M80 Ring Road Trail
If you have any questions about plans to move the transmission towers, or the North East Link Program please visit our Community Information Hub at 17 Watsonia Road or call us on 1800 105 105
North East Link and the M80 Ring Road Completion are heating up over summer
with rail system upgrades forming part of an 8-week construction blitz – in a major step towards getting the Hurstbridge rail line at Watsonia ready for North East Link
From 11pm Friday 31 January until the last service on Thursday 27 March
buses will replace trains between Heidelberg and Eltham on the Hurstbridge Line while crews upgrade a range of operational and rail systems – including track and overhead traction infrastructure
Crews will work around the clock to lay a new track slab
install communication and safety systems as well as build out the rail corridor abutments
paving the way for the project to extend the rail tunnel beneath Greensborough Highway
This major construction blitz will put the extended rail tunnel on track for completion in mid-2026. When complete
the Watsonia rail tunnel will become the third longest in Melbourne
People across Melbourne’s north-east are asked to allow extra time and plan their journey by checking the PTV or VicTraffic apps before they travel
The North East Link tunnels, the M80 Ring Road Completion and the Eastern Freeway Upgrades will be complete in 2028
we're completing the M80 Ring Road in Greensborough
The completed M80 Ring Road will take 19,000 cars and trucks a day off Greensborough Road
with traffic passing under Grimshaw Street
Elder Street and Watsonia Road – keeping local roads for local trips
Two new interchanges at the M80 Ring Road and Grimshaw Street will ease congestion and slash travel times
with dedicated lanes for local trips and express lanes to North East Link
cycling and public transport connections will make it safer and easier to move around Melbourne’s north-east
passengers will benefit from comprehensive upgrades to safety and reliability as part of plans to extend the rail tunnel where it crosses under Greensborough Highway in Watsonia
some activities can only be performed when trains are not running
with buses replacing trains on sections of the Hurstbridge Line at various times
The completed M80 Ring Road will be built over the Hurstbridge Line between Grimshaw Street and Elder Street in Watsonia
the existing rail tunnel will be extended to nearly half a kilometre long
The nearby Grimshaw Street bridge over the rail line will also be rebuilt and widened
The new extended rail tunnel will be the third longest on Melbourne’s train network
behind the new Metro Tunnel and the City Loop
The extended rail tunnel is driving maintenance work on almost five kilometres of the Hurstbridge Line between Macleod and Greensborough stations
Safety and reliability upgrades for passengers on the Hurstbridge Line include modernising tracks
wires and signalling to replace assets that are over 100 years old in some sections
Works to extend the rail tunnel and rebuild the Grimshaw Street bridge are now underway and will continue until 2026
M80 Ring Road Completion will deliver improvements to all forms of transport and make it quicker and easier to move about the area
Drivers will benefit from more lanes on the new Grimshaw Street bridge to make it easy to access Greensborough Highway
North East Link and the M80 Ring Road using the new Grimshaw Street interchange
Over 10 kilometres of new and upgraded shared paths will create better local connections for walkers and cyclists
with new underpasses at Grimshaw Street and a new Nell Street bridge to improve safety and accessibility
the pedestrian rail crossing at Wattle Drive in Watsonia was rebuilt as part of safety upgrades on the Hurstbridge Line
The new crossing is fully accessible with an active safety system including lighting
emergency gates and alarm bells to warn of approaching trains
Some upgrade works can only be carried out when power to the train line is turned off for the safety of workers
There will be planned disruptions at these times with buses replacing trains on sections of the Hurstbridge Line
Disruptions are coordinated with partners including Metro Trains and the Level Crossing Removal Project to minimise impacts for passengers
Plan your journey by visiting ptv.vic.gov.au or call 1800 800 007 before you travel
Weekend disruptions will also be required at times
the Victorian Government has delivered more train services
and better connections on the Hurstbridge Line
Works are underway in Watsonia to upgrade the Hurstbridge Line
During work hours there may be varying levels of noise
dust and intermittent vibration coming from the rail corridor
The project has strict requirements to manage these construction impacts with real time monitoring to protect the local community and environment
If you have any questions please call 1800 105 105 or visit the Hub at 17 Watsonia Road
We have a number of major construction sites as we deliver the M80 Ring Road Completion
This fact sheet outlines what we are doing to manage construction impacts and travel disruptions as we build the M80 Ring Road Completion
The project will pass through traffic under local roads from Greensborough to Watsonia for a seamless connection to North East Link – taking 19,000 cars and trucks off Greensborough Road each day
If you feel you are experiencing excessive impacts from construction, we encourage you to contact the project team on 1800 105 105 as soon as possible
All works are planned and managed in line with the project’s Environmental Performance Requirements (EPRs)
The EPRs identify the impacts of project construction and how they will be managed
These were developed in consultation with stakeholders before works on the project started through the Environmental Effects Statement (EES) process
verified and audited by an Independent Environmental Auditor
We meet Victoria’s stringent air quality standards
Air quality will be regularly monitored to ensure it complies with strict Environmental Performance Requirements (EPRs)
You may notice some vibration when we're working nearby
There are strict requirements in place to minimise disruption and avoid damage to buildings
Managing contaminated material is a normal part of major construction
We’ve conducted thousands of soil tests to understand ground conditions
but in the event that unexpected material is found
we have processes to manage this safely to protect the community and our workforce
crews will set up an exclusion zone and monitor air quality to ensure there is no risk to our workers or the public
Licensed removalists will attend the site wearing personal protective equipment
They are trained to safely handle and dispose of any hazardous materials that may be present
in line with strict EPRs and EPA guidelines
We're working hard to retain and protect as many trees as possible
We work with qualified ecologists and arborists to determine which trees need to be protected and which trees need to be replaced through new planting
To maintain access and car parking for residents in local streets
we've built dedicated car parks with over 900 spaces for our workers in our site compounds
To keep traffic moving on freeways and arterial roads
sometimes we need to carry out works at night
Although we follow specific noise requirements and plan carefully to avoid noisy works at night
Impacts to nearby residents and businesses are managed by a range of measures
including changing the time of planned works
providing respite periods or offering temporary relocation
and using noise barriers or changing construction methods to reduce noise
If you ever have concerns about the amount on noise, call us straight away on 1800 105 105
We use a system called SiteHive to monitor noise
vibration and air quality across our worksites
These smart devices have cameras and microphones that help us identify sources of excessive noise
which means we can place them in areas we predict may have higher impacts
These dedicated routes are carefully planned to minimise impacts on traffic
To keep road users safe and keep local traffic moving
we’re installing a new temporary signalised intersection on Grimshaw Street
We work closely with North East Link to plan truck movements and routes that minimise disruption to the local community
you may notice changes to some of the roads you are familiar with
particularly on and around Greensborough Highway
Greensborough Bypass and the M80 Ring Road
There may also be changes to walking and cycling paths
Our community Hub at Watsonia is a one-stop shop for project information and enquiries
Visit anytime or contact our project team to make an appointment
As part of planning for North East Link we're proposing changes to local roads in your area
we heard that retaining 2-way access at Nell Street and Greensborough Road is important
We've developed an updated design to do this
improving local access once North East Link is built
As part of this proposed design we need to slightly widen the Greensborough Road Reserve at Nell Street
Before we widen the intersection at Nell Street
we need to seek approval from the Minister for Planning to amend the Banyule Planning Scheme
We've prepared a draft Planning Scheme Amendment (PSA) as part of this process
Planning Schemes set out how land can be used and developed
The Nell Street PSA is now available for your comment
Public consultation on the Planning Scheme Amendment will commence on Tuesday 19 April and finish on Tuesday 17 May 2022
You can view the documents and submit comments on the Engage Victoria website or by posting your submission with a cover letter to North East Link Program
All submissions must state the name and the address of the person submitting
Please note that all submissions will be treated as public documents
All local councils have planning schemes in place
Planning schemes set out how land can be used
including what can be built on and under it
North East Link Program will seek approval from the Minister for Planning for a PSA to facilitate the updated design at Nell Street and Greensborough Road
To build North East Link and for Nell Street to retain access to Greensborough Road
the intersection needs to be widened to maintain safety for drivers and pedestrians
This increases North East Link’s project boundary requiring a Planning Scheme Amendment
We're updating the design at Nell Street based on what we heard from the local community. We're working directly with residents impacted by the design change. Locals can provide feedback on the design change at Engage Victoria
The Nell Street design changes will impact some trees
These trees will not be removed until major works to complete the M80 and build a new Grimshaw Street intersection begin in 2024
The final design by the appointed contractor will seek to keep as many trees as possible
Major works for the M80 Ring Road Completion is expected to start in 2024
North East Link community engagement will continue to keep local residents updated as planning and construction progresses
If you have any questions about the Planning Scheme Amendment process, please call 1800 105 105, email community@northeastlink.vic.gov.au or visit the North East Link Watsonia Hub at 17 Watsonia Street, Watsonia
Whitehorse Crime Investigation detectives have charged three people after a series of RSL burglaries across Melbourne
sets of keys and personal property from six commercial venues
Police will also allege that they compromised the telecommunication and security systems at the Watsonia
and Pascoe Vale venues to gain access to the buildings
detectives issued search warrants at properties in Prahran and Brunswick West
where they located and seized a vehicle and arrested a man and two women
A 38-year-old Brunswick West man has since been charged with five counts of burglary
A 31-year-old Brunswick West woman has been charged with five counts of burglary and theft
A 33-year-old Prahran woman has been charged with five counts of burglary and theft
possess imitation firearm and two counts of deal with proceeds of crime
They were all bailed to appear before Heidelberg Magistrates’ Court on April 28th
Information and Events for Seniors throughout Australia
Contact us: newsdesk@australianseniorsnews.com.au
We're building the North East Link Tunnels from Watsonia to Bulleen
taking traffic and trucks under instead of through suburbs
we'll be using a technique called mined tunnelling for about half a kilometre
Mining machinery will work in the rock layer deep underground
excavating the tunnels in sections and installing supports as we work
This fact sheet explains how we’ll build this section of the tunnels as people continue to live and work above
and key steps ahead of work starting in 2024
The mined tunnels in Bulleen have been carefully designed to link to the Manningham Road interchange to the north and the Eastern Freeway interchange to the south
Improvements to both interchanges in response to community feedback have let us design a straighter route for the tunnels closer to Bulleen Road that links to:
The route for the section of tunnel from Bulleen to Watsonia to be built using tunnel boring machines (TBMs) is being confirmed now
and we'll be out talking to people in the area later this year
To build the mined section of the North East Link Tunnels in Bulleen
large machines called road headers will chip away at the rock layer deep underground
To support the tunnels as they’re built
we’ll be excavating the tunnels in sections
This is called a sequential excavation method (SEM) and is a common technique used to build mined tunnels
concrete will be sprayed across the roof and sides of the tunnels (shotcrete) and supports will be drilled into the surrounding rock to reinforce the tunnel structure
The top of the tunnels will be up to 30 metres at their deepest point
That's around the height of a 8–9 storey building
Some people and places directly above or very near where works are happening underground could experience minor levels of vibration
but we’ve done a lot of work to assess the likely impacts and it is unlikely to cause damage to properties
Electronic monitors at the surface will be used during construction to help manage works underground
People near tunnelling works will also be offered a building condition survey before construction starts
In the unlikely event building damage does occur
If your property is above or near the North East Link tunnels
you will continue to use your land as you do now
If you are thinking about building on your property
an additional step in the planning permit process may be needed for certain works
the usual approvals through your local council would still apply
with a step to check what’s planned won’t affect the tunnels
like adding an extra storey or pool will likely be able to go ahead
like multi-level units with a significant basement car park structure would need extra consideration
To include the extra step in the planning permit process
the area covered by Design Development Overlays in your local planning scheme will be adjusted to align with the new tunnel route
The overlays protect the tunnels from potentially damaging works above ground and were approved in December 2019 after the project’s Environment Effects Statement (EES)
The area where the overlays apply will be updated to align with the new tunnel route
we'll be in touch with residents to confirm where the overlay is required
If you’re in the area where the tunnels will be built
are planning on building on your property and have questions now
With thousands of tunnels operating around the world and millions of people living above them with no impact on their daily lives
we know tunnels can be built safely and without affecting buildings and properties above ground
Before we start work to build the mined tunnels
NELP needs to acquire land deep underground. This is called strata acquisition and does not affect ownership of land at the surface
Land at a depth of 15 metres below ground will start being acquired towards the end of 2023
we’ll be in contact to let you know before the strata acquisition process starts
Strata acquisition will take place in accordance with the Major Transport Projects Facilitation Act 2009
Where land is acquired at a depth of 15 metres or more below ground
This is consistent with what we know about modern tunnelling
with people above tunnels being able to continue to use the land at the surface as they do now
We're completing the M80 Ring Road in Greensborough including a seamless connection to North East Link
building temporary fencing and setting up site compounds to establish safe work zones
To keep traffic moving during the day on Greensborough Highway and the M80 Ring Road
some works have needed to take place at night
we'll be able to undertake most works during the day helping to minimise impacts to locals and keep traffic moving
To make space to build the Watsonia Road landscaped bridge and connection to the North East Link tunnels
we're moving the Watsonia Road intersection and realigning Greensborough Highway closer to the former Watsonia Station car park
We’ll also prepare to move underground utility services such as sewerage
we’ve already started works behind traffic barriers in the former Watsonia Station car park
we’ve been removing existing infrastructure and installing new conduits
pits and groundwater wells for utility services
works will happen over weeknights and weekends on Greensborough Highway and Watsonia Road
and lane and road closures will be in place at times
you will be able to access Greensborough Road businesses between Devonshire Road and Richards Avenue from the northbound lanes
The temporary realignment will be in place until mid–2026
We’ll make further changes to the intersection as construction progresses
From 9pm Friday 23 to 5am Monday 26 August
Watsonia Road will be closed between Devonshire Road and Greensborough Highway
Greensborough Highway will be reduced to 1 lane in each direction between Elder Street and Powley Parade
Delays of up to 20 minutes are expected so we encourage you to plan ahead and allow extra travel time
lane closures and reduced speeds at times on:
so please follow all signage and directions from traffic controllers
the existing rail tunnel needs to be extended
we've upgraded almost five kilometres of rail tracks and signalling between Macleod and Greensborough stations
These changes will help improve the safety and reliability of Hurstbridge Line services
Works to build the extended rail tunnel and other upgrades on the Hurstbridge Line will be ongoing as part of major construction to complete the M80 Ring Road including new lanes
smart technology and a seamless connection to North East Link
Some activities can only be carried out when trains are not running and power to the train line is turned off for the safety of workers
there will be planned disruptions with buses replacing trains on sections of the Hurstbridge Line at various times
Plan your journey by visiting ptv.vic.gov.au or call 1800 800 007 before you travel
We’ll carry out most of our works during the day
although some extended hours and night works will be required
particularly when working near live traffic
There are strict controls in place to manage construction impacts when working at night
If you ever have concerns about construction impacts, call us straight away on 1800 105 105
The community will still be able to shop local and support businesses during construction
We're working with local traders on how best to support them and keep customers coming through the doors
To find out what Watsonia has to offer and support your local businesses, visit our Watsonia traders directory.
Before major construction can begin in some locations
we need to relocate underground and overhead utility services such as power
Moving these services will provide the necessary space to complete the M80 Ring Road and protect essential infrastructure during construction
We're coordinating with utility service providers to minimise planned disruptions
these may be required at times with advance notice provided to affected properties
You may notice temporary closures and access changes while we’re in the area
Our community engagement team is out speaking with local people about works in the area and how we can provide support during construction. If you have any questions or would like to speak with us, please call 1800 105 105 or visit us at:
If you require a translator or interpreter, you can phone us on 03 9209 0147
Contact us through the National Relay Service (extensive list of call options) and request to call our Contact Centre 1800 105 105
See the Australian Government's Accesshub website for information about accessible services for people who are deaf
hard of hearing or have a speech impairment
Stay updated about the North East Link Program with the key announcements and milestones
We’re getting ready to start construction of the North East Link Tunnels later this year
As we prepare for major tunnelling construction
this update outlines upcoming works in your area including Greensborough Road
we’ll need to assemble and launch tunnel boring machines (TBMs)
These huge machines will dig the North East Link Tunnels well below the ground
ensuring the community and local businesses can continue to operate above ground
The North East Link TBMs will be launched from the east side of Greensborough Road near Lenola Street
and Winsor Reserve will also be used to support construction works and tunnelling
we'll start to prepare construction sites and compounds in Watsonia
Macleod and Yallambie ahead of major work later this year
We'll also be making changes to Greensborough Road that will be in place during construction
We’ll be keeping the local community updated as we move closer to getting these works underway
and our community engagement team will be out and about talking to nearby residents and businesses
See the map on the fact sheet for more details
we'll be preparing to realign Greensborough Road between Wattle Drive and Watsonia Road
This will allow us to build the launch box where the TBM parts will be lowered into and the TBMs assembled
The small car park closest to Watsonia Road will close at the end of May (the Watsonia Station car park will remain open)
You'll see us out talking to traders and residents about these works as planning progresses
We expect these works to be completed in late September
with the changed traffic conditions in place for a number of years
we'll start preparing the site north of Lenola Street in Macleod
ahead of major piling and excavation work later in the year
Piling involves heavy machinery and cranes to bore deep holes which are filled with concrete
The piles will form the support for the launch box
you’ll see us start to secure the area where the launch box will be excavated and the surrounding compound will be built
with machinery and materials to be brought and stored on site
We'll be building a large acoustic shed at Winsor Reserve later this year
This shed will support the TBMs once they start tunnelling on the other side of Greensborough Road
As the TBMs make their way underground toward Bulleen
the dirt they excavate will be transported via a fully enclosed conveyor system over Greensborough Road to the shed
it will be safely loaded onto covered trucks inside the shed and securely carried off site
The acoustic shed will be constructed to minimise noise
The playground and Tuckfield Court path at the western side of the reserve will remain open and some large established trees on the western and southern side of the reserve will also remain
Construction compounds will be established along Greensborough Road from Watsonia Road to Blamey Road
You'll see site offices and dedicated worker facilities going up
plus storage areas being prepared to support works in the surrounding areas
To construct the North East Link Tunnels and interchanges
some trees and vegetation will need to be removed along Greensborough Road with strict environmental performance requirements in place
We've designed the project to keep trees wherever we can and to maximise opportunities for new trees to be planted – including new parklands along Banyule Creek and the Yarra River and 700 new trees for the new Greensborough Road boulevard
Borlase Reserve will continue to be used as a site compound to support major tunnelling works and construction of the new Lower Plenty Road interchange
you'll see site offices and storage areas being constructed
Large machinery will also arrive on site ready to support the start of piling works from late in the third quarter of 2022
Piling involves workers and construction equipment boring huge support columns into the ground to allow deeper digging to safely commence
Drysdale Street will remain closed from Greensborough Road to Borlase Street for several years while works are taking place
All construction site access will be from a purpose-built entry at Lower Plenty Road
no construction vehicles will access the construction site via Borlase Street
New walking and cycling detours will be in place while the tunnels are being built to ensure pedestrians and cyclists can move safely around the area
2 bus stops on Route 513 at Torbay Street and Greensborough Road will close in both directions for several years due to works in the area
For more information visit Public Transport Victoria or call 1800 800 007
Sometimes we may need to work outside these hours and we'll let you know beforehand
We'll notify you before work starts nearby with more information on what time and days we'll be working
We're planning our work to minimise disruption to the local community and road users wherever we can
noisy works will be contained inside the purpose-built shed
Hoardings will also provide some noise mitigation for nearby residents
the purpose-built shed will help contain dust from construction
Most roads within works areas will be sealed to minimise dust movement
Trucks carrying dirt from the tunnels will be covered
we'll provide plenty of notice and have traffic management plans in place to minimise disruptions as best we can
Light - Shields will be used to minimise light spill into homes
Night works - If night or out of hours work is required
we will ensure noise is kept to a minimum to reduce disturbance to residents
We’ll also let you know about any night works in advance and discuss support measures with you
Parking - Dedicated worker car parking is built for each construction area
enough for all workers to ensure they don’t park on local streets
You may have received a letter from the Spark team offering your home a complimentary property condition survey
The report produced will provide an independent record of the condition of your property on the date of the inspection
If you received a letter and would like a complimentary inspection of your property, call us on 1800 105 105
We'll continue to provide the local community with information about construction as it progresses
Our community engagement team will continue to be out and about talking to people about works in their area and how we can support you during construction
you may sometimes see us out capturing photography and videography
including the use of drone and time-lapse cameras
With construction planning well progressed
the North East Link Project is finalising a Voluntary Purchase Scheme for property owners who will be most affected by impacts of both construction and final project design
This means some people in particular homes
in particular circumstances are eligible for the Government to purchase their home
Once the details for this area are finalised
the North East Link Project will be in touch with eligible property owners with more information about the process and how they can participate if they choose
The Urban Design and Landscape Plan for the North East Tunnels is on exhibition from Wednesday 11 to Tuesday 31 May
Make your submission online at Engage Victoria by 5pm Tuesday 31 May 2022
You can also visit a display and talk with our team at the Watsonia Community Information Hub or the Veneto Club
Watsonia Hub reopened on Wednesday 2 October
The hub underwent some major renovations to set the building up for the next 8 years
Turning what was once a bank branch into a fully accessible
Come talk to us about North East Link in our new community space
Grab a free sausage from 10am until noon on Saturday 19 October
Open Monday to Friday from 10am to 5pm or make an appointment by calling 1800 105 105
Police have arrested and placed charges after a Narre Warren man was assaulted by a Wattle Glen man in a road rage incident in Watsonia last month
it is believed the 32-year-old Narre Warren man in a grey Holden 4WD was travelling along Grimshaw Street when he collided with a Holden hatchback around 3:20pm
then got out of his car and allegedly assaulted the male victim before smashing the victim’s car window with an axe
He has since been charged with driving while suspended
reckless cause of injury and reckless conduct endangering serious injury
he was also charged with assault with a weapon
the use of a controlled weapon with excuse
and nine times with the possession of a drug of dependence
heading into an unknown direction of travel
He was remanded to appear at Heidelberg Magistrates’ Court today
Two major work sites in Watsonia and Macleod have been established to support North East Link tunnelling works
We’re preparing to build Victoria’s longest road tunnels
the North East Link tunnels will take traffic and trucks under our suburbs and give local roads back to the local community
we’ve extended the North East Link Tunnels to Watsonia
we're focused on preparing for the arrival of the tunnel boring machines (TBMs) late this year
To ensure the TBM launch site at Watsonia is ready
there will be 2 purpose-built facilities constructed
An acoustic shed will be built on Winsor Reserve ready to store and remove dirt and rock excavated from the tunnels
we will build a tunnel segment storage shed to house the pre-cast concrete segments that will become the tunnel walls
We’re working closely with nearby residents to ensure construction disruptions are minimised wherever possible
Read on for more information on how these sites will be set-up this year and how they'll be used to support tunnelling from 2024
The massive TBMs need a lot of space and equipment to launch and get to work below ground
The site at Watsonia is the only area near the tunnel entrance big enough to house all the equipment needed to dig out and remove the dirt and rock as we build the tunnels
The site also provides more direct access to arterial roads
meaning fewer construction vehicles on local roads
There will be more than 1000 deliveries of equipment and TBM sections
as we get ready to assemble the 2 massive tunnelling machines on-site before they are launched below ground
Once the TBMs start working deep underground
each TBM will work 24/7 throughout the year and move up to 15m each day
we'll also be building a 550-tonne gantry crane to lower the TBMs into the launch box
The gantry crane is over 30m high and will span the full width of the launch box which is almost 50m
The main gantry beams will be delivered in 2 pieces before being welded and assembled on-site
The gantry crane will be in place by late 2023 ahead of major tunnelling works from early 2024
The massive TBMs are transported from the Port of Melbourne in segments
they are joined together and placed on a temporary platform (‘cradle’) before being lowered in and launched
A large shed is needed at the TBM launch site to store the pre-cast concrete segments that make up the tunnel walls
We'll install around 125 pre-cast concrete segments as our TBMs tunnel each day
The TBM places these curved wall segments along the dug path
ensuring the tunnel is supported and watertight
These wall segments are poured off-site and stored in a shed until they are ready to be installed
The shed will be located north of Yallambie Road
The huge cutter head on the front of the TBM rotates
with hydraulic cylinders pushing it forward
Hardened cutter discs mounted on the cutting head do the actual work of breaking away the soil and rock
Conveyor belts and pipes inside the TBMs will take the rock and soil to the end of the machine and then to the surface
the dirt and rock will be carried along an enclosed conveyor belt over Greensborough Road
where it will be loaded onto trucks and taken off-site to be re-purposed or disposed of
There are strict Environmental Performance Requirements to manage noise and vibration from tunnelling
ensuring that people can continue to enjoy their homes as they do now while the TBMs pass through
A large acoustic shed will be used to store and remove dirt from the tunnel
the excavated dirt will come to the surface on a continuous enclosed conveyor system
The conveyor will carry the dirt over Greensborough Road to the large acoustic shed
Trucks will enter the shed and be loaded with the dirt and rock
The acoustic shed will operate 24/7 and be big enough for more than 10 trucks
You will notice an increase in trucks in the Watsonia area as they continuously move in and out of the shed
The new signalised intersection on Greensborough Road will give trucks dedicated
safe access and turning space to keep other traffic moving
Both the shed and the conveyor belt will be acoustically treated and enclosed to contain noise
light and dust impacts to nearby residents
with trucks using the new traffic lights on Greensborough Road only
We know this is a big change for the local area while we build the North East Link Tunnels
we have increased hoarding heights and moved equipment and worker facilities further away from residences
We have retained around a quarter of Winsor Reserve as public open space during construction
The playground at the western side of Winsor Reserve and the path through to Tuckfield Court will remain open for local use
We’ve also kept as many of the large established trees on the south and west side of the reserve as possible
We'll be speaking to local residents soon about what they would like to see on the shed once it is built – including potential artwork
Winsor Reserve will be reinstated and returned to the community
We acknowledge that we’re working in residential areas and remain committed to supporting our neighbours and minimising the impact of construction works wherever we can
While some of our sites will eventually operate around-the-clock
they will do so in accordance with the program’s Environmental Performance Requirements (EPRs) determined through our extensive Environmental Effects Statement (EES) process
truck movements and maintaining local access
Mitigation measures will be put in place to manage dust
will minimise these disruptions and keep residents and workers safe by clearly defining the construction areas
We'll be out talking to local residents throughout the year and giving regular updates on construction
A Voluntary Purchase Scheme is available to property owners most impacted by both construction and final design of North East Link
Any decision to sell your home to the State Government is entirely voluntary and we are available to speak with eligible residents about this
Home > Spark Consortium launch first north east link TBM
Tunnelling has begun on Melbourne’s North East Link
with the first TBM now digging the 6.5km road tunnels between Watsonia and Bulleen
It’s the first of two Herrenknecht machines
and 4000 tonnes are among the biggest in the southern hemisphere
and the North East Link TBMs have been named Zelda and Gillian after 2 groundbreaking local women
TBM Zelda and TBM Gillian will dig approximately 10m per day and up to 45m underground
The tunnels will be built using 100% renewable electricity
and dirt and rock from the tunnels will be re-used across North East Link and other transport sites where possible with a significant amount of spoil also helping rehabilitate a former quarry at Point Wilson and the former Orica site in Deer Park
the TBMs will install tunnel lining made of approximately 44,000 concrete segments that have been made locally in Benalla
The machines will be driven by the Spark Consortium
which was awarded the contract to deliver the North East Link Tunnels towards the end of 2021
The $11.1bn North East Link’s twin 3-lane road tunnels will connect the M80 Ring Road to the Eastern Freeway
At 6.5km long – twice the length of the Burnley tunnel – they’re set to be the longest road tunnels in Victoria
North East Link is the biggest ever investment in Melbourne’s north east – changing the way people move around Melbourne
Pioneering Underground Technologies - Herrenknecht AG is the technology and market leader in mechanized tunnelling
Herrenknecht delivers cutting-edge tunnel boring machines for all ground conditions and in all diameters - ranging from 0.10 to 19 meters
More Information | info@herrenknecht.com | +49 7824 3020
and website in this browser for the next time I comment
Δdocument.getElementById( "ak_js_1" ).setAttribute( "value"
11/04/2025
Centralny Port Komunikacyjny (CPK) has awarded the contract for the excavation of a new High-Speed Rail (HSR) tunnel in Łódź…
07/01/2025
AECOM has announced it has been selected by Dragados UK to serve as the lead designer on the first stage…
27/01/2025
The UK’s Department for Energy Security and Net Zero has announced that it will work with the UK’s Nuclear Decommissioning…
The latest from the Tunneling Journal direct to your inbox
TGS Media LtdThe Old LibraryWebster HouseDudley RoadTunbridge WellsTN1 1LEUnited Kingdom
© Tunnelling Journal. All Rights Reserved. Privacy Policy / Terms & Conditions. Admin
In Watsonia, Macleod and Yallambie, works are stepping up as we prepare for major construction of the North East Link Tunnels
Piling works have started and we're continuing to build new lanes on Greensborough Road to keep traffic moving right through construction
North East Link will fix the missing link in our city’s freeway network
We've kicked off establishing our site compounds in Watsonia and Yallambie – all in preparation for major tunnelling in 2024
we're realigning Greensborough Road and piling the foundations for the Tunnel Boring Machine (TBM) launch box
This will help create space for us to lower the massive TBM into place
while keeping traffic on Greensborough Road moving alongside construction
we're making room for the simpler tunnel interchange at Lower Plenty Road and bringing large machinery and equipment on site to support tunnelling works
We're working closely with residents and traders as works progress
Read on to see what will be happening near you
Download the fact sheet (PDF, 731.6 KB) to view the map in detail
We’re realigning a 300-metre section of Greensborough Road to make room to build the launch box for the Tunnel Boring Machines (TBMs) while keeping traffic moving right throughout construction
On the east side of Greensborough Road between Watsonia Road and Yallambie Road
we’re preparing the launch box for the TBMs ahead of their expected delivery in late 2023
we’ll assemble and launch them on their journey south in 2024
the dirt they excavate will come to the surface on a continuous enclosed conveyor system
The conveyor will carry it over Greensborough Road to a large acoustic shed at Winsor Reserve
the dirt will be safely loaded onto covered trucks and moved offsite
Soon we'll start preparing the area and laying the foundations for the acoustic shed
To manage truck and traffic movements and to keep locals safe
a new set of traffic lights will be installed just north of Torbay Street
The playground and Tuckfield Court path will remain open for local use
we'll work with the community to reinstate the reserve into a sporting and recreation space
The ventilation structures for the North East Link Tunnels will protect the health of the local community and drivers using the tunnels
The northern tunnel ventilation structure will be located near Blamey Road on former Department of Defence land in Yallambie
We're preparing the site for construction of a ventilation shaft to connect to the tunnels underground
We’re preparing the site so we can build the ramps and the tunnels for the new Lower Plenty Road interchange
The interchange ramps will be built using a method called cut and cover
We’ve just finished 6 months of site investigation and geotechnical testing to help us better understand the area’s geology and site conditions
More than 11,000 soil and rock samples were taken from over 2000 locations
This information is helping inform detailed tunnel design
We’re planning construction to minimise traffic disruptions so you can keep moving throughout works
We’re installing new traffic light intersections along Greensborough Road to allow trucks to safely enter and exit our sites
We'll also keep reviewing traffic light sequencing to keep traffic moving
planning truck routes that avoid local roads
and using haul roads within work sites to keep as many trucks as possible off local roads
we’ll have safety barriers in place to keep people and road users separate from our works
We’ll install signs to guide pedestrians and drivers through changed traffic conditions and detours
we’ll have traffic controllers and reduced speed limits to help you travel safely
please allow extra travel time for your journey and be mindful as you move around the area
Sometimes we’ll need to work at night from 7pm to 6am
We'll reach out to businesses and traders before any night works start with more information on what time and days we'll be working
Community projects big and small will benefit from the new North East Community Fund
Applications have closed for the first funding round
and there will be another funding round in 2023
The fund will support projects and provide lasting community benefit to areas most impacted by construction
For more information, visit North East Community Fund
kindergartens and early learning centres near our works now have access to nursery vouchers as part of a $50,000 program to support more green spaces as North East Link is built
We've partnered with Yarra View and Bushland Flora Nursery
Our arboriculture specialists will also work to help them choose suitable tree species and locations
timber and mulch to local community groups and organisations from the trees that were removed
including 50 logs to Banyule City Council for playground furniture
Watsonia shops are staying open for business during works
North East Link Program and major tunnelling contractor
are supporting traders by partnering with Watsonia Traders Association and surrounding businesses to keep people shopping local throughout the works
Visit Watsonia Shops for the latest promotions
We’ll continue to provide the local community with information about construction as it progresses
Our community engagement team are out talking to people about works in their area and how we can support residents and traders during construction
17 Watsonia Road, Watsonia10am to 5pm, Monday to FridayFind us on Google maps
or contact our project team to make an appointment
Sign up for project updates
Add articles to your saved list and come back to them any time
I visited my old suburb of Watsonia recently and found a place in flux
waiting to see what will happen when the North-East Link’s tunnel project meets the Western Ring Road later this decade
the government bought huge swathes of land on Melbourne’s suburban fringes to house families of returned World War II service personnel
which comprised little more than paddocks and a railway station
It was subdivided and the lots sold cheaply to hundreds of veterans who
built modest homes in which to raise their children
had begun in crowded inner-suburban multi-generational homes
Because most of the veterans were of a similar age
I couldn’t walk through my gate without tripping over a friend
or being smacked in the head by a stray ball from a game of street tennis
we free-ranged over the open fields that would become North Watsonia
or joined others on the long hot walk down to the Greensborough swimming pool
The suburb might have been largely flat and charmless
but our treeless streets rapidly greened under serious gardening
Picture the Aussie equivalent of a Norman Rockwell painting: fathers pushing manual lawnmowers and bonding over front fences; mothers
swapping family news and arranging to perm each other’s hair
In the streets around us there were the haves and have-nots: cars or no cars; telephones or no telephones
Houses with televisions had windows that flickered blue
Our neighbours had flickery windows months before we did
they would invite us in to watch their marvel
fathers visited the old hall in Morwell Avenue that served as a kindergarten during the week and an RSL sub-branch after the dance classes had packed up on Saturday afternoons
shiny RSL attracting poker machine fanatics like moths to a supernova
The rail line and Greensborough Road slashes the suburb in two
some schools and the earliest homes; the other
with its small group of shops and slightly younger houses
Homes in Watsonia are getting bigger.Credit: Jason South
We were fortunate to be in the section with the Watsonia Road shopping strip
a much-patronised milk bar and a gift shop where I could lay-by cheap
ridiculously kitsch ornaments to give my mother
The patient owner let me pay them off a few pennies at a time
a solicitor operates from that premises and the banks are gone
a surprising number of needs are met in Watsonia Road
Greensborough Plaza is only 10 minutes away
a riffle of shock vibrated through our meat-and-three-veg lives when a Chinese takeaway opened on Lambourne Road
Good reports were relayed back from daring early adopters
Soon we were ordering our chow mein and fried rice
which the shop’s owner ladled directly into our saucepans
Thai and wine bar offerings were unimaginable then
But bigger things are afoot in Watsonia: a spanking new town square is slated for the top of Ibbottson Street
the shops across the road and early designs including a story pod
It’s just 30 minutes to the city by train and has green spaces
Dad’s lovingly tended garden is overgrown and next door
an enormous new residence looms over our little weatherboard
The excited couples who moved their families here mid-century are mostly gone
and the modest homes they were so proud of are slowly being replaced by far larger houses
hopefully disgorging another generation of kids and balls onto the streets
but a different Watsonia no doubt serves its residents well
This article is part of our “Life in the ’burbs” series.
The Opinion newsletter is a weekly wrap of views that will challenge, champion and inform your own. Sign up here
waiting to see what will happen when the North-East Link\\u2019s tunnel project meets the Western Ring Road later this decade
the government bought huge swathes of land on Melbourne\\u2019s suburban fringes to house families of returned World War II service personnel
I couldn\\u2019t walk through my gate without tripping over a friend
swapping family news and arranging to perm each other\\u2019s hair
which the shop\\u2019s owner ladled directly into our saucepans
It\\u2019s just 30 minutes to the city by train and has green spaces
Dad\\u2019s lovingly tended garden is overgrown and next door
please \\u2013 for one brief shining moment
The Opinion newsletter is a weekly wrap of views that will challenge
Our North East Link Community Information Hub is now open at 17 Watsonia Road
While renovation works are happening at the hub
you can still drop in to see the designs and concept drawings from the September 2018 project update and chat to the team about the North East Link project
Visit our community hubs page for more information
You can also contact us by emailing community@northeastlink.vic.gov.au or calling 1800 105 105
You can now click/tap WATCH to start the live stream
You can now click/tap LISTEN to start the live stream
You can now click/tap LATEST NEWS to start the live stream
Investigations are underway after a man was found dead after a house fire in Watsonia last night
Press PLAY to hear the full details from police
Emergency services were called to the Daours Court home just after 11pm
A male resident was able to safely evacuate the property
but the body of a man was found inside once the fire was extinguished
Anyone who witnessed the incident is urged to contact Crime Stoppers on 1800 333 000
we’ll be busy in Watsonia in coming months as part of works to build North East Link
We'll be working closely with service providers to build a new mobile phone tower
install underground telecommunication services
and add new car spaces at Watsonia Station
We’ll also be moving underground cables and pipes on local roads and building a site compound in Frensham Reserve to support these and other works happening nearby
Managing works well and minimising disruptions as much as we can
will be a key focus as we get these important works done safely
We've developed a design that delivers even better outcomes for local people
including a longer tunnel to Watsonia and a tree-lined Greensborough Road boulevard
Access to the station platform and bus stop will be unchanged as we move essential services and build new car spaces at Watsonia Station
Some car spaces will be closed at times but the car park will stay open with only minor detours in place
Some accessible parking spaces may also be needed during the works
and we'll provide alternatives close to paths and crossovers
Our worksites will be a safe distance from people and parked cars
and we’ll be installing temporary fencing on all sides to keep them secured
We know how important train station parking is and will provide updates as the works progress
We'll be building 24 new car spaces with lighting and CCTV security cameras on the former site of the high-voltage transmission towers
These spaces will provide alternative parking during works in the northern car park
We'll be installing underground telecommunication services in the northern car park
Works will happen during the day and sometimes overnight
We'll help service providers to build a new mobile phone tower in the northern car park and remove the current tower nearby
There will be minor changes to the car park layout with 3 new car spaces added
We'll set up a site compound to support works happening in the area
It will have temporary fencing on all sides to safely enclose sheds
The site compound will be accessed via Elder Street and Frensham Road
We'll be installing underground telecommunication services on Nell Street
These works are expected to happen during the day
We'll be installing underground gas services on Watsonia Road
These works are expected to happen overnight
We're carefully planning our works to minimise disruptions
we'll be speaking with local traders at Watsonia Shops about what to expect and will continue to support them staying open during construction
We’ll be using traffic controllers and signage when working near roads and paths to safely guide people through the area and maintain access as much as possible
There will likely be some noise during works to move underground cables and pipes
and we’ll notify you before this happens
We’re not expecting any mobile network or gas outages during these works
however your service provider will let you know if this changes
We're getting ready to reopen the doors to our Watsonia Community Information Hub
with a range of COVIDSafe measures in place
Keep an eye out on our social media for an opening date
Our friendly team are looking forward to chatting to locals about upcoming works in the area and the new North East Link design
Don't forget to support the local traders at Watsonia Shops while you're there
Victoria’s longest road tunnels will fix the missing link in Melbourne’s freeway network
We’ll also complete the Ring Road in Greensborough
build Melbourne’s first dedicated busway and the North East Trail
In response to community feedback we’re building longer tunnels and simpler underground interchanges with more room for parklands
wetlands and a tree-lined Greensborough Road boulevard
As well as extending the North East Link tunnels further north
an extra 1.9km of the overall tunnel length will now be built using Tunnel Boring Machines (TBMs) – keeping more work below ground and less disruption above
A massive upgrade to the M80 Ring Road will improve traffic flow with new lanes
up-to-date technology and 2 new green bridges connecting locals to brand new train station parking in Watsonia
We’ll also rebuild and upgrade 2.5km of Greensborough Highway on both sides of North East Link – keeping local roads for local trips
Works are continuing safely on the North East Link Program with COVIDSafe plans in place to help protect workers and the community. Strict processes are in place to check and record the vaccination status of workers entering construction sites. For more information about coronavirus COVID-19, please visit coronavirus.vic.gov.au
Sign up to our e-newsletter to stay up to date with current works and disruptions happening in Watsonia
The North East Link mega-highway will permanently divide Watsonia
according to residents who are bitterly disappointed that new designs for the $16.5 billion toll road leave an eight-lane trench splitting their community
Victoria’s largest road project will stretch 10 kilometres from Bulleen to Greensborough when it opens in 2028 and include 6.5 kilometres of tunnels
It will widen the Eastern Freeway to up to 20 lanes
Hesham Mobarek from the Watsonia Traders Association
in front of where the North East Link tunnel will emerge
the state government released detailed designs for parts of the project including the road’s northern end
where it will connect to the Western Ring Road
The tollway will emerge from the tunnel just south of the neighbourhood shopping centre in Watsonia
16 kilometres north-east of the Melbourne CBD
and run as an eight-lane road trench along the current alignment of Greensborough Road
a pharmacist and president of the Watsonia Traders Association
said the new designs failed to properly connect the east and western sides of the community – was a key object of the project’s urban design strategy
“We’re gutted; we really do feel cheated,” Mobarek said
“They’re supposed to be connecting neighbourhoods
with a horrible trench disconnecting the community.”
Watsonia locals say the North East Link road trench will divide their community.Credit: North East Link
Mobarek said two “land bridges” the project promised at Elder Street and Watsonia Road were tokenistic and narrow
and failed to lead directly to the central shopping strip and library next to Watsonia Station
“For years they’ve been talking about amazing big green bridges to connect the communities
but this falls really far short of that – especially relative to other areas of the project,” Mobarek said
About 40 to 50 per cent of customers at the shopping strip came from the other side of Greensborough Road
Watsonia Station has a small footbridge across the rail tracks leading to the local library and has also been earmarked for a multistorey car park
But the train station has unexpectedly been left out of the design plans and replaced with what Mobarek described as a “purple blob”
Banyule Council Mayor Peter Castaldo said it was difficult to assess the full impact of the North East Link project without knowing what would happen to the station
and agreed that Watsonia would be “cut in half” under the current design
“The design fails to put local people first and has not provided a well-connected and integrated design,” he said
“The landscaped land bridges in the plans don’t go nearly far enough
and getting from one side of Watsonia to the other will require walkers and cyclists to cross over two major roads.”
Castaldo said Banyule Council would continue pushing during the three-week design consultation period for more of the highway trench to be covered over to create green space
The North East Link project extended the underground tunnels by 1.9 kilometres in 2021
which saved open and green space in communities further south
Mobarek said the fact efforts to enhance community amenities in other sections of the project were not being made in Watsonia showed the community was being treated like “second-class citizens”
A spokesperson for the North East Link Project said increasing the tunnel further would extend the disruption for years and require more houses to be demolished
The council’s proposal to cover the highway trench between Elder Street and Watsonia Road would require a ventilation structure that would be an eyesore for the community
local traders and council for the last four years to develop a project that will take 19,000 cars and trucks a day off Greensborough Road and deliver major improvements to how the local community moves around,” the spokesperson said
adding that the Watsonia Station car park design would be part of a future plan for the area
The state government says the new toll road will be completed in 2028
and will shorten some road journeys by up to 35 minutes
The first segments of two tunnel boring machines arrived in Watsonia last month and will begin boring the two 6.5-kilometre tunnels to Bulleen in the middle of next year
Get the day’s breaking news, entertainment ideas and a long read to enjoy. Sign up to receive our Evening Edition newsletter here.
Victoria\\u2019s largest road project will stretch 10 kilometres from Bulleen to Greensborough when it opens in 2028 and include 6.5 kilometres of tunnels
the state government released detailed designs for parts of the project including the road\\u2019s northern end
said the new designs failed to properly connect the east and western sides of the community \\u2013 was a key object of the project\\u2019s urban design strategy
\\u201CWe\\u2019re gutted; we really do feel cheated,\\u201D Mobarek said
\\u201CThey\\u2019re supposed to be connecting neighbourhoods
with a horrible trench disconnecting the community.\\u201D
Mobarek said two \\u201Cland bridges\\u201D the project promised at Elder Street and Watsonia Road were tokenistic and narrow
\\u201CFor years they\\u2019ve been talking about amazing big green bridges to connect the communities
but this falls really far short of that \\u2013 especially relative to other areas of the project,\\u201D Mobarek said
But the train station has unexpectedly been left out of the design plans and replaced with what Mobarek described as a \\u201Cpurple blob\\u201D
and agreed that Watsonia would be \\u201Ccut in half\\u201D under the current design
\\u201CThe design fails to put local people first and has not provided a well-connected and integrated design,\\u201D he said
\\u201CThe landscaped land bridges in the plans don\\u2019t go nearly far enough
and getting from one side of Watsonia to the other will require walkers and cyclists to cross over two major roads.\\u201D
Castaldo said Banyule Council would continue pushing during the for more of the highway trench to be covered over to create green space
Mobarek said the fact efforts to enhance community amenities in other sections of the project were not being made in Watsonia showed the community was being treated like \\u201Csecond-class citizens\\u201D
The council\\u2019s proposal to cover the highway trench between Elder Street and Watsonia Road would require a ventilation structure that would be an eyesore for the community
\\u201CWe\\u2019ve worked closely with the community
local traders and council for the last four years to develop a project that will take 19,000 cars and trucks a day off Greensborough Road and deliver major improvements to how the local community moves around,\\u201D the spokesperson said
entertainment ideas and a long read to enjoy
After closing its doors earlier this month to make some improvements the Watsonia Hub has reopened
We’ve made a few improvements to the space to help keep people informed as works on North East Link progress – adding more project maps
project timelines and the latest construction information
Drop in and chat to us about any project questions you have or ask us about employment opportunities. You can also complete our skills and jobs enquiry form
Watsonia Hub17 Watsonia Road, Watsonia. Opening hours: 10am – 5pm, Monday to Friday. Find us on Google maps
The first parts of the massive tunnel boring machines (TBMs) that will dig the North East Link tunnels have completed their journey by sea to the Port of Melbourne and have been transported to their new home in Watsonia
the first TBM segments travelled from the Port of Melbourne to Watsonia on oversized trucks in a convoy known as a ‘superload’
over 4m high and more than 9m wide and travel at speeds between 5km/h and 40km/h
This is the first of more than 20 superloads that will need to travel from the Port of Melbourne to Watsonia over the next 6 months
The TBM segments that are used to build these massive machines will arrive progressively in 3 shipments over the coming months
Details will be provided ahead of each overnight superload delivery
so that road users can plan ahead and avoid disruptions
the 2 TBMs will take around 6 months to assemble on site
with the parts lowered into the ground by a 550-tonne crane
the TBMs will then work day and night as they dig their way to Bulleen – with the community having the opportunity to help name the TBMs later this year
We’re starting works on the M80 Ring Road Completion
including a seamless connection to North East Link
The M80 Ring Road Completion will take 19,000 cars and trucks a day off Greensborough Road
New interchanges at the M80 Ring Road and Grimshaw Street will ease congestion and slash travel times
10km of walking and cycling paths will help locals get to schools
As we prepare to start major construction this year
crews are busy establishing work sites across the project area
The Frensham Reserve offset car park for Watsonia Station will open in early April
This will allow us to close Watsonia Station car park in April and use the space to build the M80 Ring Road Completion
Accessible parking spaces and the bus stop will remain within the existing Watsonia Station car park near the station entrance
We’ll rebuild a new car park next to the station
ready for people to use when the project is complete in 2028
The local community will be able to see and give feedback on the design before construction on the new car park starts
We'll carry out most of our works during the day
When working extended hours and doing night works we'll provide more information to nearby residents beforehand
We’re continuing work to set up site compounds at AK Lines Reserve and Gabonia Avenue Reserve in Watsonia
workforce parking and material and equipment storage needed to support major construction
Both reserves will be returned to the local community with improvements when the project is completed
To ensure local clubs that use the reserves can continue to thrive during construction
we’ve built new multimillion dollar facilities at Binnak Park and Greensborough College nearby
For the safety of road users and our workers
we’re building work areas with access points and haul roads for construction vehicles along the M80 Ring Road
Greensborough Bypass and Greensborough Highway
Crews will remove selected trees where necessary and clear topsoil to install traffic barriers and fencing
Setting up work sites allows us to start utility relocation works
install temporary noise walls and realign roads
The centre median on Greensborough Highway
will soon be removed to realign Greensborough Highway to create space for major construction
Reduced speeds and lane closures will be in place over several weekends from Friday 15 March
Traffic management will be in place to help people move safely through the area
For more information check bigbuild.vic.gov.au/disruptions
A longer rail tunnel will run under an upgraded Greensborough Road and new express lanes to North East Link
We'll continue to work in and around the rail corridor this year as we prepare to extend the rail tunnel
buses will replace trains on sections of the Hurstbridge Line
For further details and to plan your journey, please visit ptv.vic.gov.au or call 1800 800 007
The second round of North East Community Fund recipients have been announced
More than 45 projects will receive over $2 million worth of funding to support their local community
Watsonia Primary School and Watsonia North Primary School are three recipients of the latest round of funding
Concord School will use their $65,000 grant to build a quiet nature play zone to help students to connect with the environment
Watsonia Primary School will get almost $55,000 to upgrade the school’s playground and apply acoustic treatments to the community hall
Watsonia North Primary School will use their $75,000 grant to build an indigenous garden and outdoor learning space
We’ll release information later this year about more funding opportunities in 2024. For more information, please visit northeastlink.vic.gov.au/communityfund
will be planted for the M80 Ring Road Completion
We’ll plant indigenous trees and vegetation from local regions and use fast-growing native species to help shade walking and cycling paths
create new wetland areas and return local reserves
We'll also launch the next round of the Backyard Tree Planting Program for residents and community groups later this year
This program is on top of work already underway to plant at least two trees for every one removed for construction
In an Australian first for the construction industry
we’ve successfully trialled 100 per cent recycled cardboard and plastic hoarding panels at our Gabonia Avenue Reserve site compound in Watsonia
We're now installing this type of temporary hoarding in various locations across the project
Compared with traditional plywood hoardings
recycled hoarding is expected to reduce carbon emissions by up to 70 per cent
seven kilograms of waste is diverted from landfill
Recycled cardboard hoarding also provides better noise protection than traditional plywood hoarding
we’ll recycle the hoarding and seek opportunities to reuse panels on other projects
We're assembling the first pieces of the tunnel boring machines (TBMs) into the launch box at Watsonia before tunnelling begins later this year
We're also constructing an 80-metre tower crane at Lower Plenty which will help support deeper digging at the far southern end of the site
Thanks for sharing your feedback on the Urban Design and Landscape Plan (UDLP) while it was on exhibition in October last year
We’re working through your comments now and looking at where we can make changes to the project design to reflect what local people want to see in their area
We’ll be providing an update later this year ahead of major construction
Receive updates about the M80 Ring Road Completion
Watsonia Tennis Club is set for a major upgrade to its facilities, thanks to the North East Community Fund
The Fund will contribute $91,000 to the tennis club
which will be used to create a new accessible entrance to the clubrooms and toilets
and create an accessible area for community BBQs and club events
The upgrades will allow everyone to access the club’s existing hardcourts – which are some of the only tennis courts in the area that are a suitable surface for wheelchairs
The upgrades are all about being more inclusive and allowing everyone to play tennis
Club President Danny Hadjiantonakis says the club is committed to helping everyone in the community enjoy the benefits of tennis
“The North East Link community fund will allow us to upgrade our facilities for those with disability to be able to allow everybody to come and use the club.”
Club Member Greg Bakopoulos says the upgrades will be fantastic for people who want to try wheelchair tennis
“It’s going to make things a hell of a lot easier and hopefully it’s going to bring other people
To find out more about the North East Community Fund and other projects supported, visit North East Community Fund
Waking up at 3.30 am is not good for the body at the best of times
I felt it was going to be a great day if I was able to capture the the moment and seize the day before the sun rose to illuminate everything on its journey across the heavens
At 4.30 am I walked across the road to the Watsonia RSL with a warm cup of coffee to reduce the chill in the air and warm the cockles of my heart
As I made my way across the car park dividing us
I observed the headlights of one vehicle being parked
while the RSL community bus rolling up with the driver sauntering into the RSL for a cup of coffee
The first thing I noticed is the large TAB sign on the wall of the RSL and I frowned that it has come to this
A sign of the times when corporations and interested players influence RSL board decisions
it is what it is and we mere mortals can but keep our thoughts to ourselves as life continues changing at a pace that at times is beyond our comprehension
The roar of a motorcycle was heard at the roundabout
a vehicle drove passed stopping momentarily at the pedestrian sign
I observe solitary figures approaching the RSL entrance
Adrian Hook the radio technician arrived on the scene to set up the communications for the day service
The roar of the motorcycle continued in the distance
skirting the roundabout about 40 metres to the East
followed by the odd vehicle making its way towards the South along Watsonia Road
Dennis Gambrellis the Vice President of 96.5 Inner FM operating out of the Warringal Shopping Centre at Heidelberg
(Dennis’s ancestors came from the island of Kos in Greece) arrives
a presenter of the same radio station has come along to observe the proceedings
George is an ex National Serviceman Officer who served with 5/7 RAR
sharing information from a bygone era and it was interesting to note that as we age how one mellows with time
Throngs of people begin to arrive many with their wives and partners sporting their medals proudly on their chest
Three buses pulled up and parked in front of the RSL lights flashing
idling their engines in preparation to advance to their destination
A young lass in uniform arrives with her mother who is a member of 39 Army Cadet Unit
overcoats and warm clothing keeps the cold of dawn at bay
I am wearing my Spartan jacket over my warm t-shirt with a collar
This keeps the warmth in and the cold at bay
The radio station plays magnificent background music which I am advised is ADAGIO in G minor
followed by an introduction by the President of the Heidelberg radio station
A wonderful introduction to those beginning to arrive
After a while music began to be beamed from a huge screen located at one end of the RSL
I bade farewell to George and returned home for a quick bite to eat and to the warmth of home
Our home is a mere 75 paces directly across from the RSL
giving us prime view of the ANZAC Day proceedings
At 5.59 am I returned back to the RSL for the dawn service
followed by the President opening the ANZAC Day service for 2023
His introduction was followed by the Lords prayer
Colin Brooks the local State member and Minister was next cab up the rank
reminding all those present of Gallipoli and of what the nation suffered as a result of those who paid the ultimate sacrifice
Colin Brooks went through the various generations and described each generations service to the nation and that of the world
Another presenter gave an interesting outline of all the conflicts that Australia had been involved in and thanked veterans who had served
who is alleged to have spoken the immortal words dedicated to those who fought at Gallipoli
history has demonstrated that those fine and passionate words were not uttered by Kemal Ataturk but have somehow been constantly repeated over the years and became part of the ANZAC legend
the colours of Dawn were slowly rising from its slumber
navigating across the roof tops in the distance
One could see the crowd of people that had come to the service and it was a wonder to behold
In my 30 years of coming to the Watsonia RSL for the Dawn service
this was by far the most numerous that I had ever witnessed
I looked at all the faces trying to to identify someone from my youth
The president spoke again and there was utter silence
followed by the last post and a minutes silence
of families who had lost loved ones and of mates since gone onto another field of play
My thoughts were interrupted by a bugle sound that signalled for the time honoured one minutes silence
Thoughts of goodwill for all mankind and of mates long gone meandered through my brain
The silence was pure gold and looking up into the East
I could see that the suns rays began to strike the heavens and the arrival of a new day
The next bugle call brought the silence to an end and the beginning of another year of hope
At the end the New Zealand and Australian national anthems were played
As the suns rays began to reach us I saw that the crowd had swelled considerably over the space of some thirty minutes
They had come from all over the place in their dribs and drabs; the young
families and veterans congregating in the car park and using it as a parade ground for visitors and passer by alike
I would say that over 1500 people had arrived to attend the ANZAC Day Dawn service followed by Gunfire Breakfast at a small cost of $5 per head
A far cry from the Gunfire breakfasts held by that indomitable and much loved character of Bruce Ruxton
a time when many from all walks of life would stroll to his office to attend the Gunfire breakfast
I must add that I was chuffed to be a part of Todays Dawn Service and very pleased to see so many people of all ages attending
never given up and always fight the good fight
Major upgrades at Binnak Park are now complete with a new pavilion, cricket nets and turf to keep sports clubs playing and thriving while North East Link is built and beyond
The new pavilion will provide a great view for spectators as well as female friendly change rooms
The upgrades also include fencing and new lighting for the AFL/Cricket oval and improved car parking on the northern and southern sides of the site
You’ll have the opportunity to come and see these massive upgrades for yourself once Coronavirus restrictions have eased
We're looking forward to moving in and making the most of these fantastic new facilities
The new pavilion offers a great view of the ground and we’re excited to see it in action
More than 40 trees have been planted to green the area as part of these upgrades
These facilities will be enjoyed by the community
and Plenty Valley Cricket Club and Watsonia Sporting Club who will be temporarily relocating during major construction of North East Link
They will join the park’s existing sporting group
The new look Binnak Park is part of our $68 million investment in local sports upgrades
supporting the north east community as we build North East Link
For more information about upgrades to Binnak Park and other sports facilities in the area, visit our sports facilities page
It should be noted that this information is current at the time of publication, however changes may occur. Please visit our website for the latest updates
The best local news sent straight to your inbox every workday
Make a donation and support the future of journalism and media diversity in the ACT
herbaceous garden plant that grows easily in our climate
herbaceous plant that emerges in spring ready for flowering
It’s from the South African iris family and its reed-like foliage can be used as a background plant that puts on a magnificent display of tall
fragrant flowers that slowly open and last for several months
They’re available in many colours – pink
reds and lilacs – but my favourite is white
which gives a bright contrast in the garden
They grow from a corm underground and can multiply very easily
the better the soil the better the flower display
Dividing should be done if the flowering display declines over the years
It should be tackled after flowering with a sharp spade and transplanted directly into a well-prepared garden bed
Watsonias are tough and don’t need a lot of water; they’re drought tolerant when established and
there’s one weed species – Watsonia meriana – that should be removed from the garden
It has orange to reddish-purple flowers and grows more singularly but multiplies fast and
Manually pulling up the whole plant and corms before flowering will help in eradicating this pest plant
which is now on the weeds of national significance list and is affecting natural bushlands around Australia
ONE of my favourite trees that is in flower now is the tulip tree (Lirodendron tulipifera)
A hardwood native to the eastern US and used for veneers
it’s only grown in Australia as an ornamental tree
Tulip trees are a medium-to-large size tree (up to 20 metres tall and eight metres wide) with a straight trunk and a conical crown
they are a majestic tree to have in a park or large garden but not for small gardens
they share the same spectacular flowering and like the same growing conditions – full sun and a slightly acidic soil
Its leaves have an unusual four-lobed shape
the trees burst into attractive green to orange flowers
They are drought tolerant when established and like our cold winters
There are some really beautiful specimens of tulip trees around Canberra as street trees and a few in Commonwealth Park
There are dwarf varieties – up to 10 metres tall – available overseas that would suit our suburban backyard and would make a terrific shade tree
all trees will still need watering (even after rain) to keep the moisture levels up in the soil for the warmer months ahead
Watering trees around the drip line with deep water weekly or fortnightly
is more beneficial than short watering several times a week
jackwar@home.netspeed.com.au
there’s never been a more important time to support independent journalism in Canberra
If you trust our work online and want to enforce the power of independent voices
Every dollar of support is invested back into our journalism to help keep citynews.com.au strong and free
Become a supporter
'We focus on spending time with our clients to understand how they use their home and their specific comfort needs,' says air conditioning expert PAUL OXFORD in this advertising feature provided by Delta Air Conditioning & Heating
Size differences didn't cause any issues when the world's tallest and smallest living dogs met up for a playdate in Idaho
The ginkgo tree is in a botanical class of its own – it's not a conifer and doesn't flower or have pollen
North East Link is another step closer to slashing travel times and taking trucks off local roads
as segments of the first tunnel boring machine (TBM) have been lowered into the ground – as the project gets ready to dig the twin road tunnels
The assembly is taking place at the TBM launch box in Watsonia
where two of the largest TBMs in the southern hemisphere will start digging the 6.5km tunnels in mid-2024
The first pieces of the huge machines have been lowered into the ground by a 550-tonne gantry crane – when assembled
each 4000-tonne TBMs will be 90 metres long and more than 15 metres in diameter
the TBMs will start working their way south from Watsonia toward Bulleen
installing tunnel walls made of almost 44,000 individual concrete segments manufactured locally in Benalla
a massive amount of work is underway to prepare for tunnelling
The 200-metre-long TBM launch box in Watsonia is complete
and work has started on the underground box structures near Lower Plenty and Manningham roads where the TBMs will excavate into on their journey south
From late March drivers in Bulleen will notice changes to how they use Bulleen Road, Manningham Road and Bridge Street to allow for further works to continue on the Manningham interchange. These changes will stay in place for up to 2 years to keep traffic moving during construction. Find out more by reading the fact sheet - Changes to key roads in Bulleen
And barriers and worksites are being set up along the Eastern Freeway and M80 Ring Road
so crews can upgrade the freeways that will connect to the North East Link tunnels – to cut travel times by up to 35 minutes
We send out regular information about the progress of North East Link and works happening
We’re also helping deliver one of the biggest tree planting programs for a major road project in Victoria
The M80 Ring Road Completion will take 19,000 cars and trucks off Greensborough Road a day and give local roads back to local people
We'll upgrade the M80 Ring Road with new lanes and a new M80 interchange
A new Grimshaw Street interchange will keep traffic moving
We're also building 10km of walking and cycling paths
and two landscaped bridges to Watsonia Station and shops will make it easier for locals to get around
To deliver these upgrades some trees will need to be removed and replaced through new planting
For every tree removed for the M80 Ring Road Completion
Together with North East Link and the Eastern Freeway Upgrades
we're increasing tree canopy cover in Melbourne's north east
with the first trees already in the ground in local parks
Trees will be planted to help screen and filter views of new noise walls
support wildlife habitat and return improved open spaces where it is needed to support construction
We'll also be creating new wetland areas at the M80 Ring Road
We’ll be planting indigenous trees and vegetation from local regions
We're carefully staging our works to return open space to the public as soon as possible
We know trees are important to the local community and we're working hard to keep and protect as many trees as possible
We've reduced the area needed to support construction at the M80 Ring Road
Trist Street Reserve and Gabonia Avenue Reserve to keep more existing trees
and are maximising opportunities for new trees to be planted after construction
we will be working with qualified ecologists to plan and manage how works will take place
including to determine which trees need to be protected and which trees need to be replaced through new planting
To ensure trees and vegetation are correctly identified – and protected where possible – a rigorous process of fencing
flagging and final review by an expert arborist occurs before works start
Regular inspections are also undertaken by an Independent Environmental Auditor
Extensive field surveys will help identify animals that will need to be re-homed
qualified ecologists and animal handlers will find and safely move animals to a similar habitat nearby
Wherever possible trees that have been removed will be re-used for landscaping and urban design
or for local community and sustainability projects
If you’re part of a group that could use timber for local community initiatives
upgrade the Eastern Freeway and build North East Link
more than 30,000 trees will be planted across Melbourne’s north and east
More than 2500 trees have already been planted through our early tree planting program
Please contact us if you would like this information in an accessible format. If you need assistance because of a hearing or speech impairment, please visit relayservice.gov.au
This information is current at the time of publication, however changes may occur. Please visit our website for the latest updates.
Receive updates about the M80 Ring Road Completion.
Play Duration: 7 minutes 55 seconds7m Brought to you by
Residents of Watsonia are feeling duped after designs for a road as part of the North East Link were updated.
Pharmacy owner Hesham Morabek says the new design lacks walking access and greenery that was originally promised.
The North East Link program says Watsonia will recieve 'two green bridges'.(Supplied: Victoria's Big Build )
Download the ABC listen app to text and call your favourite live radio
Are you ready to join the thousands of companies who rely on Blue Book to drive smarter decisions
We’d love to show you what Blue Book can do for you
Drop us a line– we’ve been waiting for you
and shipper of fresh peaches in the Eastern United States
This collaboration marks an exciting expansion of Titan Farms’ offerings
introducing Certified Organic Peaches to its premium portfolio
Watsonia Farms has built a legacy of sustainability
The farm’s dedication to organic practices
and environmental stewardship makes it a natural fit for Titan Farms’ commitment to delivering the highest-quality peaches to consumers nationwide
expressed enthusiasm about the partnership
“We are thrilled to join forces with Watsonia Farms to bring organic peaches to market
Their long-standing dedication to organic farming
combined with our expertise in quality and food safety
ensures that customers will receive the best tasting organic peaches available
This partnership represents our commitment to meeting the evolving demands of today’s consumers while maintaining the high standards Titan Farms is known for.”
“Partnering with Titan Farms is an incredible opportunity to bring our organic peaches to a broader market while maintaining the quality and sustainability that have been the foundation of our farm for over a century,” said Jerry Watson
“Our family has always believed in the power of collaboration and innovation
and working alongside Titan Farms allows us to continue that legacy
We look forward to growing together and providing consumers with the freshest
best-tasting organic peaches available.”
Titan Farms will offer organic peaches in multiple pack styles
which is available with a pre-season commitment
Titan Farms looks forward to bringing premium organic peaches to consumers through this partnership
continuing both farms’ long-standing tradition of excellence
For more information, visit www.titanfarms.com
Founded in 1999 by Chalmers and Lori Anne Carr
packer and shipper of fresh peaches and vegetables
With core values focused on producing the highest quality produce in the market
you are sure to take home the freshest produce they have available
Titan Farms is the largest peach grower on the east coast
250 acres of bell pepper and 350 acres of broccoli
including long-time employees who have become part of their Titan family
has been producing top quality agricultural products for over 100 years. Joseph H
Watson’s leadership played a pivotal role in organizing peach farmers in the early stages to improve effective planting and harvesting practices
as well as introducing other new crops in the Ridge area of South Carolina. Peaches became a cornerstone crop for the Watson Family
while committing to produce at the highest quality and most flavorful. In 2005
Watsonia Farms made the significant transition to an organic farm
further emphasizing its dedication to sustainable farming practices
The Watsons are proudly devoted to the health of the farm’s land and the well-being of all customers
kathryn@goldensuninsights.com
Get access to all the news and analysis you need to make the right decision --- delivered to your inbox
The Chilean/Peruvian offshore season will wrap up over the next four weeks
Expect pricing to increase as the offshore season winds down
The Foundation For Fresh Produce held its annual Consumer Connection Conference April 28-30
tangy refreshment of California-grown grapefruit and introducing a new way to enjoy it
Instacart announced its acquisition of Wynshop
a provider of e-commerce solutions for leading grocers and retailers
Subway is stepping in to make dining decisions even easier with the return of $6.99 Any Footlong all month long
Lipman Family Farms announces the acquisition of Shelton & Sons
a trusted tomato grower based in Morristown