Developers say the project will fundamentally reshape travel in the EU for the better
cutting the time it takes to get from Hamburg to Copenhagen in half
But German advocates aren’t so sure the benefits outweigh the risks
Rødbyhavn tunnel factory in January of 2025
If the idea of driving more than 11 miles through the ocean sounds terrifying
“When you drive through the Fehmarn Belt tunnel
you will have 40 meters (approximately 131 feet) of water above you,” he said
Vincentsen is CEO of the Danish state-owned company behind the Fehmarn Belt Link
which will connect Denmark and Germany through the longest immersed tunnel in the world
Most of the funding comes from Denmark and the European Union
Unlike other passages through major waterways — such as the Channel Tunnel between England and France
which travels through solid earth beneath the ocean floor — the Fehmarn Belt will travel along a trench at the bottom of the sea
The tunnel itself is locked into place with stone and sand covering the top
Footage of construction crews shows workers casting the structure of the tunnel in concrete
They’re building the tunnel in 79 different pieces
each weighing approximately 150 million pounds
Vincentsen said that he understands that the idea is intimidating
The tunnel’s traffic will be split into two separate roadways
making it easier to respond to any issues underwater
It will also include monitors throughout in case of an emergency
it’s probably some of the most-safe areas to actually drive
Danish advocates were initially skeptical of the proposal to connect islands between northern Germany and southern Denmark
when the developers were thinking of building a bridge above the water rather than a tunnel
because we think it was maybe destroying nature and acting like some sort of barrier for the stream of water in and out of the Baltic Sea,” said Michael Kruse of the Danish Society for Nature and Conservation
Kruse said he was particularly concerned about the potential for massive ships that travel through the Baltic to hit the structure
“If you can imagine a Russian supertanker coming through the Baltic Sea and it made contact with the bridge
it could give a lot of problems with the environment amid all that oil,” he said
The company in charge of the project eventually made concessions
Kruse said environmentalists changed their stance as a result
he looks forward to being able to zip between Denmark and Germany without taking a ferry or finding a lengthy car route
The shorter distance — and the option of traveling via railway — will ultimately be better for the environment
adding that the new connection will foster cultural exchange
“It’s two cultures meeting in one project,” Kruse said
“It’s almost like you are creating a new country
But some Germans say they see things differently
with Germany’s oldest and largest environmental group
said that while a tunnel is a better option than a bridge
the project will primarily benefit the Danish side by creating jobs in one of the country’s poorest areas
is very much dependent on tourism and lives on tourism mainly,” he said
Siegert said he is concerned that rather than helping the tourism industry
the construction and traffic jams caused by the tunnel will destroy the area’s charm for vacationers
the project’s developers are moving forward
arguing that the economic benefits of a new link between the two countries outweigh any local concerns
They hope to open the tunnel to trains and cars in 2029
delivered to your inbox every weekday morning
Thanks to our sponsor
PRX is a 501(c)(3) organization recognized by the IRS: #263347402
Festival goers camped in crowded conditions and battled bad weather for much of the event
Hendrix is all smiles as he walks among festival goers
If you asked those fortunate enough to see Jimi Hendrix perform live at one of his 350 or so shows during his short career to describe the experience
words like "amazing," "electrifying," "otherworldly," "loud" and "unpredictable" would likely rank high among their descriptive choices
for his final scheduled performance — at a festival marred by technical issues
a lack of facilities and eventual cancellations — the unpredictable element was whether the guitar icon would show up at all
The event in question was the Open Air Love & Peace Festival
held over the weekend of September 4 through 6
which Hendrix was set to headline on Saturday night
This appearance would mark the final scheduled performance from Hendrix and the last incarnation of the Experience
The show saw the return of original drummer Mitch Mitchell and featured Hendrix’s army pal
The Fehmarn gig was the final stop of the band's 1970 Cry of Love Tour
Other scheduled acts on the festival bill included Sly & the Family Stone, Canned Heat, the Faces, Ginger Baker's Air Force, Cactus, and the Rory Gallagher–fronted Taste
the latter two acts would eventually pull out due to the same issues that would impact Hendrix's set
The three German organizers were inspired by the success of the Isle of Wight Festival
boasted six to seven hundred thousand attendees and at one point held a Guinness World Record for festival attendance
Hoping to piggyback on the festival’s popularity and book some of its acts
the Fehmarn organizers thought they might create a European version of Woodstock
Some reports suggest that as few as 10,000 tickets were shifted
In the end perhaps 60,000 made actually attended the event
an unexpected crush that made for uncomfortable conditions throughout the event and blocked traffic to and from the concert
Hendrix was paid 70,000 Deutsche Marks — around $160,000 in today's money — along with his travel costs in advance for the appearance
The festival's success heavily relied on him as the Saturday headliner
The organizers hoped to capitalize on the popularity of the Woodstock festival film
which had hit European theaters earlier that summer and featured Hendrix’s performance of “The Star-Spangled Banner.” As a result
the guitarist’s face appeared alone on many of the event's promotional posters
the event was plagued with power issues from the start
Severe winds and storms battered the stage throughout Saturday's sets
and it was deemed unsafe for anyone to set foot on it — let alone plug anything in — until the weather cleared
who was scheduled to take the stage at 8 p.m
eventually began his set at noon the following day — with several thousand fans holding their place in the rain for the 16 hours in between
with many still popping up online occasionally
you mothers," before shedding some light on his tardiness
"We couldn't come on last night — it was just unbearable," Hendrix explained
referencing the torrid conditions he and the band endured upon finally arriving at the site
Once Hendrix played the first few notes of the show opener
Howlin' Wolf's "Killing Floor," all appeared to be forgiven
with the Experience tearing through a stacked setlist that included classics from across his discography
such as "Spanish Castle Magic," "Hey Joe," "All Along the Watchtower," "Red House," and "Purple Haze," before closing with "Voodoo Child (Slight Return)."
The set also featured some new tracks that would eventually be released posthumously
This wasn't Hendrix's first rodeo when it came to unforeseen circumstances halting one of his performances
he was scheduled to close the festival on Sunday night
significant delays pushed his set to 9 a.m
the audience's reaction was far more forgiving — perhaps a reflection of the '69 "flower power" and "Summer of Love" energy of the time
the boos and jeers at this 1970 festival may have spoken to a harder-edged crowd reflecting the changing times — or maybe they were just fed up being stuck out in the rain
we know the Open Air Love & Peace Festival show was the beginning of the end for Hendrix
with rumors of upcoming collaborations with Miles Davis and Jimi's need to constantly evolve as a player
you can't help but wonder where he might have gone next musically
I've given this era of music everything." Suggesting that he had grown "exhausted" and jaded with his current presentation
"I can't think of anything new to add to it in its present state."
Hendrix's final time onstage would come two nights before he died
when he sat in for a couple of the closing numbers with the Animals frontman Eric Burdon and his new band War at Ronnie Scott's Jazz Club in London on September 16
1970 — a little shy of four years to the day when the then-unknown Hendrix played his first show just half a mile away at the Scotch of St
The complete audio recording of the Jimi Hendrix Experience performing at the Open Air Love & Peace Festival — sneakily captured by the organizers using overhead mics onto a reel-to-reel at the side of the stage — was eventually released in 2005 as Live at the Isle of Fehmarn and lives on as an essential document of the guitar god's final official live performance
Whether CD sales have helped recoup any of the troubled event's financial losses
Jonathan GrahamSocial Links NavigationWriterThe Editor in chief of Guitar Interactive since 2017
Jonathan has written online articles for Guitar World
Guitar Player and Guitar Aficionado over the last decade
He has interviewed hundreds of music's finest
session work and online lessons for Lick Library
“We turned the Marshall up all the way
That’s the sound.’” In a rare interview
Barry Goudreau talks creating Boston’s smash debut and his ongoing rift with Tom Scholz
“I sometimes feel a bit apologetic about it." Brian May says Freddie Mercury fought his now-classic guitar solo on one of Queen's biggest hits
It wasn't the 'magical record.'" When Kiss’s 1998 reunion album was in jeopardy
Bruce Kulick returned to the fold to save the day
Femern A/S recently released a very interesting video named ‘Fehmarnbelt tunnel – Great progress with the German portal Puttgarden Autumn 2024’
The video shows visible progress at the German portal near Puttgarden: the temporary retaining dyke that previously enclosed the northern part of the excavation pit has been completely removed
This means that the foremost tunnel section built on land now extends into the Baltic Sea
This content is available after accepting the cookies
which is being manufactured in the factory on Lolland and towed to the coast near Fehmarn
Daily news and in-depth stories in your inbox
We look back at the icon's last ever performance and which tracks he played
It's now over half century since the world lost Jimi Hendrix
The legendary guitarist died on 18th September 1970
tragically becoming a member of the "27 Club"
He was found in a basement apartment in London
having died of asphyxia while intoxicated with barbiturates
icon and rock pioneer had many brilliant moments in his short life
including his performance at Woodstock 1969
Radio X looks into the last gig the Purple Haze singer ever played
Some may think Hendrix's last gig was at the Isle Of Wight Festival, which took place on the British island between 26th and 31st August 1970
the musician then went on to play the Open Air Love & Peace Festival in Fehmarn
this show was set to take place on an Island set just North East of Hamburh and a few miles from the Danish coast from 4 to 6 September
it wasn't quite the well-oiled machine it thought it would be
and the festival was fraught with problems due to poor organisation and ticket sales
the weather broke and the festival goers who braved the trip had to contend with wind and rain
and many acts began pulling out of what was beginning to look like a disastrous inaugural event
READ MORE: What did The Stone Roses play at their last gig?
According to a reporrt on the Concerts Wiki, Hendrix didn't play the first night he arrived due to poor weather conditions and an issue with tents being too close to his stage
playing what nobody realised would be his last ever public live performance
Disgruntled with the festival as a whole and his late showing at first
the crowd are believed to have jeered and booed
kicking off his performance with a cover of Howling Wolf's Killing Floor
Hendrix launched into his cover of Bob Dylan's All Along The Watchtower
Jimi Hendrix | Canned Heat - Isle of Fehmarn (1970 | Rare Footage)
Opting for his interpretation of Billy Roberts' Hey Joe for track number four
the rocker then played Hey Baby (New Rising Sun)
Message of Love and the irresistible Foxy Lady
which was first taken from The Jimi Hendrix Experience's 1967 debut album Are You Experienced
Ezy Rider and Freedom were next up on the setlist
JIMI HENDRIX - The Last Minutes On Stage (1970) - VHS Archives
Hendrix's 13-track-setlist ended with a duo of absolute belters
with the guitar legend playing a rendition of Purple Haze and Voodoo Chile (Slight Return)
which would have no doubt swept the audience up into a frenzy
It might not have been the glitziest of festivals
but thanks to a dodgy bootleg recording by the promoters on site
it was later mixed and produced into a live album in 2005
ready to be enjoyed by generations of fans born long after Hendrix passed away
Jimi Hendrix last performance at the Love & Peace Festival 1970
Killing Floor (originally by Howlin’ Wolf)2
All Along the Watchtower (originally by Bob Dylan)4
See more More Features
Please enable JS and disable any ad blocker
Arup and TEC joint venture as the main technical advisor and consultant for the 18km-long Fehmarnbelt Fixed Link
a strategic underwater transport link between Scandinavia and continental Europe.
the tunnel will unlock opportunities for commuters
Fehmarnbelt Fixed Link will be the world’s longest immersed rail and road tunnel.
The JV has been working closely with Femern A/S for over a decade
providing specialist technical advice across a range of engineering disciplines to allow the delivery of a world class transportation system for the future. A key part of the European Commission's TEN-T programme and a priority rail corridor
Fehmarnbelt Fixed Link includes a two-lane motorway and a double-track railway for high-speed electric trains
drivers will cut down their travel time by about an hour each way compared to the ferry crossing
Rail passengers between Copenhagen and Hamburg will save about two hours on their journey
With more freight being transported by rail
the tunnel will also support a greener transportation system.
Following the signing of a bilateral treaty between Denmark and Germany in 2008
Arup was appointed as part of a joint venture with Rambøll and TEC to support Femern A/S as the principal client consultant for the tunnel design
Our initial commission comprised early optioneering
preparation of the illustrative design and identification of the technical requirements for the tendering process. Our technical support to the client continued into the pre-qualification stage and we participated in the Competitive Dialogue tendering process for the four major tunnel contracts
our role on the project continued as client advisor during the design review and construction phases right through to completion of the works
The unique scale of this immersed tunnel required an innovative design approach
the work by our JV made the selection of the immersed tunnel option preferable over the cable-stayed bridge
backed by our thorough analysis of technical
The advantages of building a tunnel included lower risks to navigational safety and lower permanent impact on the marine environment and bird migration in the region
Our tunnel ventilation strategy was also key to selecting a tunnel over a bridge
The immersed tunnel will be made of 79 standard and 10 special elements
each of the standard tunnel elements is 217 metres-long
The 200ha construction site at Rødbyhavn in Lolland
is the location for the large purpose-built production facility and the work harbour for the construction and launching of the immersed tunnel elements.
as part of a dedicated JV sustainability team
also led the upgrade of the carbon inventory for the construction phase to calculate the generated carbon emissions
Collaboration between the JV and Femern’s in-house specialists was key to delivering a project of this complexity, scale and size from design through to construction
in both on-shore and off-shore environments
The Rambøll, Arup, TEC JV has provided technical advice on a range of challenging issues, including the behaviour of the complex geotechnical conditions spanning the 18km Fehmarnbelt seabed and the interface with the structural elements
The team has also developed asset management specifications and structural health monitoring requirements with a view to optimising the future operation and maintenance of the tunnel
designed an innovative tunnel ventilation system.
Provided technical advice on a range of challenging issues, including the behaviour of the complex geotechnical conditions spanning the 18km Fehmarnbelt seabed and the interface with the structural elements
If you'd like to speak to one of our rail experts about any of the issues raised on this page or a potential collaboration then please get in touch by completing the form
Femern A/S has just released the latest Fehmarnbelt project update from the German construction site: the northernmost part of the portal at Puttgarden has been successfully flooded
This means that a part of the tunnel on the German side is now also under water
The outer retaining dike still has to be removed so that the first element of the immersed tunnel
which will be transported from the factory in Lolland to Fehmarn
can later be connected to this part of the tunnel
The construction site on the German side is much smaller compared to the construction site on the Danish side
In addition to the construction of the tunnel portal on Fehmarn
the project also includes connections to the existing road network – main road B207 and motorway E47 – and the existing railway
The local road and path network will also be adjusted and several smaller bridges and tunnels will be built to ensure passage for local traffic
Serving the tunnelling industry since 1969
The first element will be prepared for immersion by attaching two special pontoons to the ends of the element and adding more ballast concrete
and the remaining tunnel elements will be carried into the basins soon
Femern announced that the first two elements for the Fehmarnbelt tunnel have been moved from the dry dock into the large basins before the tunnel factory at Rødbyhavn
The update follows several weeks of extensive testing
involving water filling in the dry dock and the closure of the watertight gate in front of the factory
a total of 89 elements will be produced for the project
seven standard elements and two special elements
designed for the basement of the tunnel’s technical equipment
The first elements will be prepared for immersion
which involves attaching two special pontoons to the ends of the element and adding more ballast concrete to weigh it down
The remaining tunnel elements will be carried into the basins soon
where they will be kept until the main contractor
Femern Link Contractors (FLC) proceeds to final work
building and operating the fixed link across the Fehmarnbelt between Denmark and Germany
is an under-construction immersed tunnel that links the Danish Island of Lolland with the German island of Fehmarn
Work harbours are developed at Puttgarden on Fehmarn and at Rødbyhavn on Lolland
from where building materials needed for the construction project are sailed out
The project involves dredging an 18 km-long trench
where the tunnel elements will be immersed into and covered with gravel
The surplus material from the dredging will be used to build new coastal areas near Rødbyhavn and to a limited extent on Fehmarn
the Fehmarn Belt Contractors (FBC) consortium completed the digging of the trench after three years and removed around 15 million m3 of spoil from the seabed
In June, Denmark’s King Frederik inaugurated the first tunnel element
which measures 217m and contains nine segments of 24m each
The construction of the Fehmarnbelt tunnel is expected to be completed in 2029
the tunnel would become the world’s longest road and rail tunnel
Give your business an edge with our leading industry insights
View all newsletters from across the Progressive Media network
© Business Trade Media International Limited
either observed and verified firsthand by the reporter
or reported and verified from knowledgeable sources
Translations may contain inaccuracies—please refer to the original content
The first section of the world's longest underwater road and rail tunnel has been constructed
putting the project on track for completion by the end of the decade
The Fehmarnbelt tunnel will link the Danish island of Lolland with the German island of Fehmarn
It is said the tunnel will cut travel times between Scandinavia and Central Europe to under ten minutes
while contributing to tourism and both countries' green transitions
conservationists told Newsweek that they fear the ambitious new link won't live up to the developers' environmental promises
Construction began in 2020 on the Danish side
the Copenhagen-based firm charged with designing and planning the tunnel
Completion of the tunnel is scheduled for 2029
and will apparently cut travel time between the countries from 45 minutes by ferry to 7 minutes by train
Works are currently focused on dredging the tunnel trench and constructing new breakwaters in Lolland
the latter creating "around 300 hectares of new land," according to Femern
named after the 12-mile Fehmarn belt in the Baltic Sea under which it will be built
will be around 41 meters wide and sit at a depth of up to 130 meters
Denmark will be responsible for funding the project
the costs of which were estimated at €5.5 billion in 2008
which will be paid off with tolls from those using the completed tunnel
Femern told Newsweek that Fehmarnbelt link's total construction framework is now 55.1 billion Danish krone
Femern said that the tunnel had been designated as a "priority project" by the European Union, which has provided funding to several similar transit projects hoped to create a trans-European transport network
Through its through its Connecting Europe funding facility, the EU has so far granted Fehmarnbelt around $1.2 billion in subsidies for design and construction costs
Last Monday, King Frederik X of Denmark was on site in Lolland to celebrate completion of the first 217-metre sections of the tunnel
the country's transport minister Thomas Danielsen called the project "a milestone in Danish history," and said: "With the Fehmarnbelt tunnel
we get a fantastic and cross-border infrastructure project."
"Today is visible proof of how far we have come," added Mikeel Hemmingsen
the Danish company in charge of the tunnel's construction
"The Fehmarnbelt tunnel will show the way for many other major projects in Denmark and in the rest of the world."
Its developers have championed the tunnel as an investment in climate friendly transport
providing a greener alternative to air travel between Scandinavia and Central Europe
Søren Have of Copenhagen-based climate-focused think tank CONCITO
echoed these expectations and said: "While all such infrastructure projects have substantial carbon emissions from construction
some have the potential to pay it back over time
through lower emissions from reduced or changed traffic patterns
The Fehmarnbelt tunnel is such a project."
this sentiment was not shared by The Nature And Biodiversity Conservation Union
Germany's oldest environmental association
a policy officer for marine conservation at NABU
told Newsweek that the Fehmarnbelt link "contradicts a green transition."
Citing a 2020 report by the European Court of Auditors
which cast doubt on the economic viability of numerous transportation megaprojects in which the EU has invested
Böhnke-Henrichs said: "The project includes a large highway component which conflicts with the European aim to bring traffic from road to rail
is expected to attract only 1 million passengers yearly
far too little to be economically viable."
She added that the tunnel's construction risks harming "some of the most diverse reefs in this part of the Baltic Sea."
"Irrespective of the Baltic's poor environmental status
The project cuts the Fehmarnbelt marine protected area and thus disturbs refuge of the protected harbor porpoise."
Do you have a story we should be covering? Do you have any questions about this article? Contact LiveNews@newsweek.com
Newsweek is committed to challenging conventional wisdom and finding connections in the search for common ground
Newsweek is committed to journalism that's factual and fair
Hold us accountable and submit your rating of this article on the meter.
Newsletters in your inbox See all
By Railway Gazette International2024-05-14T12:00:00+01:00
EUROPE: The first of 89 concrete elements which will be assembled to form the 18 km Fehmarn Belt immersed tube rail and road tunnel between Denmark and Germany has been cast at the production site in Rødbyhavn
The 217 m element comprises nine 24 m segments and weighs 73 500 tonnes
The project will require 79 elements of this type
plus 10 special elements with space for technical equipment
‘Casting such a large concrete structure has been a long and complicated undertaking
but we’ve now demonstrated that technology and methods interact well’
CEO of state-owned project promoter Femern A/S on May 6
Dutch companies Boskalis and Van Oord have now completed dredging of the tunnel trench
which took almost three years and involved up to 70 vessels
It involved the excavation of 15 million m3 of material — the equivalent of six Great Pyramids or 6 000 Olympic swimming pools — which has been used to create 300 ha of new land at Rødbyhavn
The fixed link is expected to be completed by 2029
offering a transit time of 7 min by train and 10 min by car
INNOTRANS: Boring will be exciting at the Tunnel Construction segment of InnoTrans 2024
which will feature more than 30 exhibitors highlighting the latest ideas to make building and operating tunnels safer and more efficient while minimising environmental impact
DENMARK: The first of the buildings which will be used to produce the 217 m long
73 500 tonne concrete elements for the Fehmarn Belt immersed rail and road tunnel between Denmark and Germany has been topped out by project promoter Femern A/S and main contractor ..
GERMANY: Construction of the German side of the 18 km Fehmarn Belt immersed tube road and rail tunnel between Germany and Denmark was officially launched with a sod-turning ceremony on Puttgarden on November 29
Parliamentary State Secretary in the Federal Ministry of ..
Site powered by Webvision Cloud
M&A Seminar on Preparing Your Company for Sale Presented by Maslon LLP and Northborne Partners
visits the Fehmarn Belt tunnel construction site at Roedbyhavn on the island of Lolland
The future 11-mile rail-and-road tunnel under the Baltic Sea will link southern Denmark to northern Germany
First element of underwater tunnel linking Denmark to Germany makes progress
The Federal Reserve is expected to keep interest rates unchanged despite political pressure from President Tru[...]
The Trump administration is swiftly remaking housing policy as the U.S
Department of Housing and Urban Develo[...]
construction job openings dropped by 38,000 in March
signaling slowing labor demand amid tariffs
Trump's trade demands stretch beyond tariffs
is now an official city after a local vote
Milwaukee Mitchell Airport will start a $95.2M international terminal project this summer after delays and ris[...]
Sign up for your daily digest of Minnesota News
Efforts to reform Minnesota zoning laws fail again as local opposition blocks a bill limiting parkin[...]
will break ground this summer on The Dorian
a 190-unit apartment complex in Lake Elmo af[...]
The University of Minnesota plans to sell 60 acres at UMore Park for $8.1M to North Wind Test for a [...]
The Federal Reserve is expected to keep interest rates unchanged despite political pressure from Pre[...]
The Trump administration is swiftly remaking housing policy as the U.S
Department of Housing and Ur[...]
signaling slowing labor demand amid tarif[...]
Trump's trade demands stretch beyond tariffs
Performance contracting helps governments and schools cut energy costs
Milwaukee Mitchell Airport will start a $95.2M international terminal project this summer after dela[...]
Listen here
analysis and commentary on Minnesota business
We are the only independent daily newspaper dedicated to business reporting
Get our free e-alerts & breaking news notifications
Subscribe for access to the latest digital and special editions
your new go-to podcast to spice up your weekday mornings with relevant news
and behind-the-scenes from Brussels and beyond
From the economy to the climate and the EU's role in world affairs
this talk show sheds light on European affairs and the issues that impact on our daily lives as Europeans
Tune in to understand the ins and outs of European politics
Dare to imagine the future with business and tech visionaries
Deep dive conversations with business leaders
Euronews Tech Talks goes beyond discussions to explore the impact of new technologies on our lives
the podcast provides valuable insights into the intersection of technology and society
Europe's water is under increasing pressure
floods are taking their toll on our drinking water
Join us on a journey around Europe to see why protecting ecosystems matters
and to discover some of the best water solutions
an animated explainer series and live debate - find out why Water Matters
We give you the latest climate facts from the world’s leading source
analyse the trends and explain how our planet is changing
We meet the experts on the front line of climate change who explore new strategies to mitigate and adapt
Denmark and Germany are one step closer to being linked by the world's longest underwater rail and road tunnel
Danish King Frederik X inaugurated the first element of a future 18-kilometre tunnel under the Baltic Sea on Monday
It will link southern Denmark to northern Germany and contribute to the transport sector's green transition
The Fehmarnbelt link, which is expected to open in 2029, will also cut travel from the present 45-minute ferry crossing to as little as seven minutes by train
It will link Roedby on the Danish side to Puttgarten in Germany
with onward connections by road and rail to central Europe and the Nordic countries
Frederik unveiled a plaque at the entrance of the first 217-metre section of the tunnel, which will be submerged into a seabed trench on the Danish side later this year. He dropped a coin at his effigy into a time capsule containing objects donated by those who built the concrete elements
Sund & Baelt, the company building the Fehmarn link, claims it will be the longest submersible tunnel
It will also include an electrified train track
Cars are expected to be able to cross the Baltic Sea in 10 minutes on the four lanes and trains will do that in seven minutes
In 2011, it was decided that a link between the southern Denmark island of Lolland and the northern German isle of Fehmarn should be built as an immersed tunnel. Work on the Danish side was commissioned in July 2022
and on the German side exactly a year later
The tunnel will consist of 89 concrete elements which are being constructed at a special facility in Roedbyhavn on Lolland
dubbed North Europe's largest construction site
The Fehmarn link will cost 55.1 billion kroner (€4.8 billion) and will be paid by users in Denmark
The Danish government will decide the toll charge for the tunnel at a later stage
In recent years Denmark has built road-and-rail links to neighbouring Sweden and between two major Danish islands
In 2000, a bridge-and-tunnel link across the Oresund strait connected Copenhagen to Sweden's third largest city Malmo
road traffic opened between the islands of Funen
where Odense - Denmark’s third largest city - is located
Train traffic there started a year earlier
Video presented and narrated by Fred Mills
a sleepy German holiday island is about to be transformed by one of the largest infrastructure projects in the world
The island of Fehmarn sits just off the mainland of Germany and is separated from the south coast of Denmark by a 20-kilometre stretch of water known as the Fehmarn Belt
Construction is underway on a tunnel between the two countries that will provide the missing link in a transcontinental highway which will move hundreds of thousands of people a year and generate billions of dollars in revenue
The Trans-European Transport Network is a series of roads
railways and shipping lanes which connect every corner of the continent
One of the most important routes is the Scan-Med corridor
the central vertical axis of the network which spans 5,000 kilometres from Malta in the mediterranean to Finland's icy tundra
Along the way it drills through Alpine rock and crosses frozen seas
But follow the route north through Germany and something strange happens
Instead of driving straight up towards Sweden
you have to take a 150-kilometre loop through the whole of Denmark
unassuming stretch of water: the Fehmarn Belt
So, let’s just get this straight. There’s a transport route that stretches from near the African coast to the arctic circle, complete with some of the world’s most iconic engineering – the Brenner Base Tunnel
the Great Belt Bridge – but a small stretch of water in northern Europe is enough to create a detour the size of a country
Well, it may not look like much but the Fehmarn Belt has thwarted some of the world’s best engineers for over a century. Until now.The Øresund Bridge is one of those rare feats of civic construction: a mega structure whose architecture and engineering come together in perfect harmony to create a truly iconic piece of infrastructure. Immortalised in the 2011 drama The Bridge
it connects Denmark with the southern Swedish city of Malmö and it was while this crossing was being planned that Sweden had a big idea
Right now to get from Sweden down into Central Europe
That takes you over the Øresund crossing to Copenhagen where you change onto another train that takes you down into Hamburg in Germany
Even on a high speed train that takes about five and a half hours
Germany is Sweden’s second biggest export market
The Swedish government saw a shortcut at the Fehmarn Belt so during negotiations with Denmark a deal was struck: the Swedes would help build the Øresund Bridge if Denmark agreed to look into constructing a fixed link at the Fehmarn Belt
that wasn’t as outrageous as you might think
There’s been talk of creating a railway between Hamburg and Copenhagen since the 19th century – quaintly dubbed the Vogelfluglinie
or bird flight line – but nothing really happened until the 60s when a bridge was built to cross the short stretch of water between Fehmarn and mainland Germany
That route was then extended to a new ferry port at Puttgarden bringing trains right up to the water's edge
Amazingly the trains were then loaded onto ferries and carried over the Fehmarn Belt and onto to Denmark
The diesel trains that served the route weren’t as fast as the trains we have today
Above: Trains on the ferry crossing the Fehmarn Belt
For years afterwards there was talk about upgrading the route to a fixed link but it wasn’t until Sweden threw down the gauntlet that things got really serious and in 2008 the Danish and German governments signed a treaty to start work on The Fehmarn Belt Fixed Link
The proposed crossing would consist of a four-lane motorway and two rail lines serving both freight and high speed passenger trains
The whole thing would be funded by Denmark who would in turn collect the toll fares and run the onshore businesses
Germany would upgrade the route from Fehmarn into the mainland to allow for the new trains and traffic to pass through
which would include building another short tunnel to cross the Fehmarn Sound
It would be a once in a generation upgrade in the transport network
The Hamburg to Copenhagen corridor would be transformed into a high-speed road and rail route
the Swedes would get their shortcut to the continent
a massive detour would be wiped off the Scan-Med corridor and that
would transform the wider Trans-European Transport Network
The only thing that stood in the way was the water
Feasibility studies had been conducted as far back as the 90s and – as proved by the Øresund crossing – Denmark was pretty good at building them
The proposal they came up with was a three-kilometre long
cable-stayed bridge sitting about 65 metres above the water so that ships could still pass underneath
The cable-stayed design was similar to the Øresund Bridge but with one key difference
it would be three times as long – and that’s where the problems began
perilous ocean but the Fehmarn Belt is still pretty awkward
surprisingly deep in places and the soil conditions aren’t great for building on
Image courtesy of Dissing+Weitling / Femern A/S
To contend with the length of the Fehmarn Belt the bridge would have needed spans of over 700 metres
longer than anything which has ever been built for a combined road and rail bridge
The plan was to construct three huge pylons each just under 300 metres tall
The foundations of those would have to be built at sea in depths of up to 25 metres
Throw in poor soil conditions and a busy shipping lane and you have an engineer’s idea of hell
After careful consideration of the risk of cost overruns and the technical complexity of construction
No problem there though because the Fehmarn Belt is the ideal length for a bored tunnel
There’s a few reasons why bored tunnels are great
First off they don’t disturb anything above ground
That’s why they’re usually used for underground railways in cities but that’s also great for a place like Fehmarn which has a delicate ecosystem that could take years to recover from all the disruption caused by building a bridge
They’re expensive but they tend to be more economical the further you go
So the team set out to investigate the possibility of a bored tunnel under the Fehmarn Belt
Bored tunnels are dug by a tunnel boring machine – or TBM. The width of the tunnel depends on the TBM but something like London’s new Elizabeth line used machines around seven metres wide
Above: The drill head of a tunnel boring machine
They’re good for something like an underground railway because you have one track per tunnel
That could mean boring 5 separate tunnels at five times the cost
Very little of a train’s surface area actually sits on the track and because the wheels are made of steel
it’s one of the reasons trains are so fast and efficient
But going uphill becomes a bit more challenging
The average mainline train can drive upwards by 2.5 percent or 1 in 40
The Fehmarn Belt is about 40 metres deep at its deepest point and any bored tunnel would have to sit at least 10 metres below that
That would make the tunnel incredibly long in order for a train to travel into it
pass under the ocean and pass successfully again up the other side
A shorter tunnel would create a train track that’s incredibly steep and any train probably wouldn’t make it
So you may think with a bridge and a bored tunnel ruled out it may be time to throw in the towel
there’s one option left: the immersed tube tunnel
IMTs are made up of prefabricated concrete elements
Once made these are taken out to a trench which is dug in the seabed and sunk and sealed together
the whole thing is covered over with earth and hey presto
An IMT is a great solution for a place like the Fehmarn Belt
It’s shallower than a bored tunnel so trains have no problem passing through
You avoid the technical complexities of building a bridge and it poses no risk to shipping once it’s complete
IMTs are usually used for fairly short stretches like rivers and harbours
Keep driving over the Øresund Bridge towards Denmark and you hit a man made island and suddenly drop down under the sea into the Drogden Tunnel
It’s one of the longest IMTs in the world and it’s only four kilometres
The Fehmarn Tunnel will be five times longer
it all starts at the immense construction site at Rødbyhavn on the Danish side of the Fehmarn Belt
run by the Danish state owned company Femern A/S
it’s taken them two years just to build the work area
The star of the show is the enormous factory where the tunnel segments will be constructed
It’s one of the biggest factories ever built in Denmark
altogether covering half a million square metres
That scale is needed for the production lines that will churn out the 89 concrete tunnel elements
Once fully up and running these factories will be on 24 hours a day
seven days a week – for three and a half years
Above: The Rødbyhavn construction site with the tunnel factory under construction in the centre
aggregates and materials will be delivered to the purpose built work harbour and then taken by conveyor belt to the factories where the elements are being cast
Each element is so large it will be constructed of nine smaller segments
Once a complete tunnel element is constructed it will get rolled out of the factory and taken to a huge dry dock where it then gets floated and taken out to sea where the tunnel trench is dug
Massive ballast tanks are flooded to sink the 73,000-tonne concrete tunnel elements to the bottom of the ocean where winches will guide them to within 15mm of their targets
the trench is back-filled and the tunnel is covered in gravel to protect it
nature takes over and eventually covers the gravel bed with sand
Above: An artist’s impression of a tunnel element being taken out to sea
Once the tunnel structure is in place there’s then the small challenge of laying a motorway and railway through it
The tunnel will also be fitted out with ventilation
support and surveillance systems before it’s expected to open for traffic in 2029
thousands of cars and hundreds of trains will pass through it every day
The expected economic benefits are huge but it still all costs a lot of money
The budget for the project currently stands at USD $7.5BN
Half a billion dollars of that is coming from EU subsidies
and the rest is coming from a loan by the Danish state meaning it won’t cost Danish taxpayers a penny
Above: An artist's impression of the tunnel entrance
Denmark actually stands to gain quite a lot from this project
It’s expected that cars are going to be charged around the same as the ferry – around USD $100 for a return journey – which is projected to generate around $4BN in profit during the first 50 years of the tunnel's life
a tunnel which improves infrastructure and creates billions of dollars in profit
Well it’s not just the Fehmarn Belt’s geography the construction has had to battle
Campaigners from the German Aktionsbündnis gegen eine feste Fehmarnbeltquerung (AGFF) – action group against the Fehmarn Belt fixed link – have fought tooth and nail for the last decade to prevent the construction of any permanent crossing
This is the downside of massive construction projects
Any new mega scheme has to be built somewhere
Whether you like it or not it’s going to have a massive impact
One of the key environmental concerns regarding the tunnel is water clouding
Critics of the project argue the soil dredged during the construction will have a significant impact on the ecology of the Fehmarn Belt
“The ecology of the Fehmarn Belt is very diverse
it’s marked by a diversity of species which were believed to be extinct in the Baltic
The clouding of the Fehmarn Belt through the release of sediment and the turbidity will reduce the growth of macrophytes and plankton and have repercussions on all fauna and flora.”
Above: A dredging boat digging the trench for the tunnel
Femern A/S says sedimentation is one of the most closely monitored environmental impacts on this project
The company says it uses special dredging machines to minimise the spill and have patrol boats and monitoring stations around the dredging site to collect data on water clouding
This and other environmental data is published in real time on the Femern A/S website in an effort to improve transparency around the construction
But it’s not just the marine environment AGFF is concerned about
A big feature that is being touted about this new tunnel is that it’ll kind of provide a new green link to the continent
Femern A/S says that because the distance between Hamburg and Copenhagen is being shortened thousands of vehicles will have to drive 150km less
The new rail service will take cargo out of lorries and place them on to freight trains and the new rail link will make taking the train a more attractive option
But – and this is a big but – constructing something as ambitious as the Fehmarn Tunnel comes with a huge carbon footprint
mostly from the vast amounts of concrete being produced
2 million tonnes according to Femern A/S’ own calculations
Above: An artist’s impression of a tunnel element being cast
the tunnel will deliver a significant contribution to a green transeuropean traffic corridor by creating a 160 km shortcut
creating a viable alternative to air traffic and shifting goods from trucks to electrified freight trains
They add that they are making a concerted effort to reduce the CO2 footprint of construction
but it’s not possible to build in this scale without causing some emissions
One of these initiatives is their commitment to use 100 percent renewable energy sources for construction and operations of the tunnel
Infrastructure inevitably comes into contact with the natural world
That doesn’t mean concerns should be brushed aside but it also doesn’t mean we should never build infrastructure ever again
What opposition groups such as the AGFF express are legitimate anxieties from people living on the doorstep of one of Europe’s biggest construction projects
When there is a good case for a new megaproject
it’s important that project teams listen to concerns and work to reduce the impact of their work on people's lives and the environment as much as possible
That’s something this project has set out to do from the start
Most of the construction activity is being done on the less-populated Danish side of the water and new habitats are being built to compensate for land now occupied by the factory
Over the next decade a new route will be tattooed onto this part of the map – and for the people who use it
its convenience will erase any memory of the enormous effort that it took to make it happen
For an example of how this can happen you don't need to travel any further than the southern end of the Fehmarn
The bridge which connects the island to the German mainland was heavily opposed when it was built in 1963 as residents worried it would destroy the place’s unique character
Today it’s considered iconic and there is a campaign to save it
following fears it will fall into disrepair once the new tunnel opens
While these projects are difficult and controversial to realise when they’re first constructed they go on to have a defining impact on all of our lives
The new tunnel under the Fehmarn Belt will impact millions of people across this continent over the decades to come
Any of the controversies around its construction will likely be forgotten and the extraordinary engineering that went in will be taken for granted
as Femern A/S technical director Jens Ole Kaslund said
“My hope is just that a year after it opens
no one can remember that it was not there."
Microsoft Flight Simulator and Smiley.toerist
We welcome you sharing our content to inspire others, but please be nice and play by our rules.
Thanks! You’ll get a confirmation email from us shortly. These can sometimes go into your junk mail.
Sign up and follow us to ensure you never miss an update!
The Fehmarn Belt Tunnel will link Denmark and Germany
It's an engineering masterpiece that is set to halve journey times between Hamburg and Copenhagen
This website is using a security service to protect itself from online attacks
The action you just performed triggered the security solution
There are several actions that could trigger this block including submitting a certain word or phrase
You can email the site owner to let them know you were blocked
Please include what you were doing when this page came up and the Cloudflare Ray ID found at the bottom of this page
Danish MPs have given the green light to the construction of the Fehmarnbelt underwater tunnel which will reduce travel time between the country and Germany to just a few minutes
Work on the Danish side is now expected to start on January 1, 2021, and the tunnel — known as the Fehmarnbelt link — is now forecast to open in mid-2029, the Ministry of Transport said in a statement on Friday
Transport Minister Benny Engelbrecht hailed the MPs agreement as a "historic decision"
describing the tunnel as "a new gateway to Europe"
The 18-kilometre tunnel will link northern Germany to the Danish island of Lolland which are separated by the Fehmarn Belt — a strait in the western part of the Baltic Sea
Construction was postponed by six months because of the COVID-19 pandemic
The 52.6 billion Danish kroner (€7 billion) project will feature an electrified double-track railway and a four-lane motorway
It will allow trains and cars to cross the strait in just seven and ten minutes respectively
a ferry takes about an hour to make the crossing
The Fehmarnbelt link will be built as an immersed tunnel
The concrete elements will each weigh 73,000 tonnes and will be towed by large tugboats before being lowered down
The Fehmarnbelt link will be the longest tunnel of its kind anywhere in the world
If you have questions regarding your subscription of European Security & Defence contact our subscriber service:
By Railway Gazette International2021-01-11T09:00:00
EUROPE: A virtual groundbreaking ceremony was held on January 1 to officially mark the start of construction of the 18 km Fehmarnbelt tunnel between Denmark and Germany
Already have an account?
You’ve reached your limit of content for the month
Register for free now
Some are necessary and we can’t switch them off
Others help us to provide you with the best possible service
We use cookies to personalise content and ads
to provide social media features and to analyse our traffic
We also share anonymous information about your use of our site with our social media
By accepting cookies you will be helping us to continue to provide you with the best possible service
Adapteo has begun installing the accommodation and amenities at the specially created “FLC Village” in Denmark
for the thousands of workers employed on the Fehmarn Belt tunnel currently being built between Germany and Denmark
The temporary and adaptable buildings supplier was appointed by FLC Tunnel Group North to supply and manage the flexible buildings for the new 30,000m2 village
which is currently under construction on the Danish island of Lolland
would be ready for occupation by the end of this month
The company will erect a total of 42 flexible units at FLC Village
These will provide Fehmarn Tunnel workers with housing
a hair salon and recreational spaces such as leisure facilities with changing rooms and a canteen
“We are very proud to be able to offer high quality and flexible housing and recreational spaces to the people who are working with this enormous infrastructure project
“It is the largest order in the history of Adapteo
and we are happy and humble for the opportunity to be a part of the realization of the tunnel that will further conjoin Denmark – and by extension
the Nordic countries – with the continent.”
Adapteo created a completely new design for the FLC Village buildings.
“The buildings are 9x3 metres and include private rooms for the residents
and recreational spaces and outdoor terraces
“This is not something that we have done before
so it is great to see how the buildings are coming along
Our construction is proceeding according to plan
and we look forward to welcoming the workers to their new accommodation soon.”
The 18km long Fehmarn Belt tunnel is an undersea road and rail link
the immersed tunnel will stretch across the Bay of Kiel in the Baltic Sea
and upon completion will connect the German island of Fehmarn and the Danish island of Lolland
Estimated to cost around €7.4 billion, the project is being funded by the Danish government, with some funds being provided by the European Union through its Connecting Europe Facility
To accommodate the new transport link, a new harbour at Rødbyhavn has also been under construction since November 2019
Following an investigation, the financing for the project was cleared by the European Commission in March 2020
allowing developer Femern A/S to activate the main construction contracts with the Femern Link Contractors
You’ve reached your limit of premium article views this month
Become a Plus Member today and gain further access to the content
Off Highway Research - Market research
Unique marketing services that create demand for your products locally
Marketing Services
Download Media Kits
there is a feud between Sweden and Denmark - and on a cold October day in 1644
bloody showdown between these two hereditary enemies takes place
maritime archaeologists investigate the wrecks prior to the construction of a tunnel between Lolland and Fehmarn
The exhibition ‘In Smoke and Flames’ is the result of several years of research
carried out by Danish and German researchers from the Viking Ship Museum and the Archäologisches Landesamt Schleswig ‐ Holstein
With the discovery of the three shipwrecks
we can bring to life the gruesome events that mark the beginning of the end of Denmark’s power in the Baltic Sea
A visual staging of a dramatic painting from the naval battle
Fragments of bronze guns destroyed by fire and explosion
An impressive ship model of a Danish warship
which underline the importance of fire as a decisive element of naval warfare
A timeline that lets you follow the course of history
From Christian IV increasing the Sound Toll and the Swedish invasion of Jutland
to the fateful battle in Fehmarn Belt and the subsequent peace negotiations
the maritime archaeological investigations of the shipwrecks in 2012 and 2020
The story continues in the online finds catalogue and essays from maritime archaeologists and experts in naval war history
And with a series of small films produced during the construction of the exhibition
we take a look behind the scenes and show glimpses of how the new special exhibition was created
» Opening hours and prices
» Become a friend of the museum
» Subscribe to the Newsletter
The Viking Ship Museum in Roskilde is the home of five world famous Viking ships and is the Danish museum for ships
seafaring and boatbuilding culture in ancient and medieval times
Privacy and cookie policy | Subscribe Newsletter Vikingeskibsmuseet: Vindeboder 12 . DK-4000 Roskilde | Phone.: +45 46 300 200 | museum(at)vikingeskibsmuseet.dk
Femern A/S is activating the main construction contracts with Femern Link Contractors (FLC) with effect from January 1
the project owner said in their latest release
This means that construction of the large scale tunnel element factory at Rødbyhavn can get underway
November 2019 saw the start of the main construction phase of the Fehmarnbelt tunnel when the contract with the Dutch contractor consortium
for the new work harbor at Rødbyhavn came into force
“The harbor is expected to be completed by the end of 2021
the EU Commission approved the financing model for the entire Fehmarnbelt project,” Femern said
Activation of the contracts is being carried out with due respect for the ongoing German approval process of the Fehmarnbelt project
To be built in northern Europe and connect Scandinavia with Germany
the Fehmarnbelt will be the world’s longest immersed tunnel
The infrastructure will close a major gap in the European transport network
energy consumption and create a new region in Europe
while also fostering the development of new nature and recreational landscapes by Working with Nature concepts
By Railway Gazette International2020-02-10T06:00:00
DENMARK: Fehmarn Belt rail and road tunnel project promoter Femern A/S has appointed SNC-Lavalin Group company Atkins to provide multidisciplinary railway consultancy services for the construction of the 18 km fixed link between Denmark and Germany
By Railway Gazette International2021-11-30T12:25:00
GERMANY: Construction of the German side of the 18 km Fehmarn Belt immersed tube road and rail tunnel between Germany and Denmark was officially launched with a sod-turning ceremony on Puttgarden on November 29
at the ironically titled Love And Peace Festival
Festival goers camp in a Citroen 2CV car at the Open Air Love And Peace Festival
Jimi Hendrix's final show was at a festival marred by terrible weather
machine-gun fire and marauding Hell's Angels
it’s because I’m always running” – Jimi Hendrix interviewed in The Times
On September 5, 1970, the day before he played his last ever gig, UK music paper Melody Maker published an interview with Jimi Hendrix.
The interview had taken place some days earlier: on August 29, the day before Jimi played the Isle Of Wight Festival
an appearance that marked the first day of a week of intensive touring
bassist Billy Cox and drummer Mitch Mitchell would play six major gigs in three countries across Europe.
but the tour was cut short after concerns for the health of Cox: on September 1
someone had spiked his drink with LSD and he was still paranoid and exhausted over a week later
the tour was cancelled and Cox returned to the States
but they’d already played their last gig together
violence and arson by the time Hendrix got there on September 6 for his last live performance
UK student-turned-stagehand David Butcher was relatively sheltered from the chaos
Sign up below to get the latest from Classic Rock
”On the second day this English guy who was manager of one of the other bands decided to pull out,” remembers Butcher
“The Hell’s Angels were causing so much trouble – they were ransacking the office and giving free tickets to everybody
but basically they kind of took over and there was a lot of trouble
For a while afterwards I wondered if we’d imagined it
I still think that Voodoo Child – the long version with Stevie Winwood and Jack Casady – is one of the most amazing pieces of rock music ever.”
David and his friend Dave Philip travelled to Düsseldorf where Philip’s father was stationed in the army
the two made full use of the house and the times
when we saw a poster for this festival in Fehmarn
We didn’t have any money so we sat down at this typewriter and we concocted this letter to the festival organisers saying that we were passionate about music – which was true – and that we were doing a thesis on music as a unifying force and visiting loads of festivals…”
a couple of backstage passes arrived in the post
The two hitchhiked all the way up to Fehmarn
and we’d been hitchhiking for a day and half
and we just found a spot on the grass to lie down
got into our sleeping bags and crashed out
We’d crashed out in what was the middle of the car park area and during the night hundreds of cars had appeared around us…”
Jimi’s journey to Fehmarn hadn’t been filled with as much good fortune
Hendrix hadn’t wanted to come to Europe in the first place
but manager Michael Jeffrey had convinced him that his new Electric Lady studios needed an injection of cash – the answer was a short tour that began at the Isle of Wight festival and continued in Denmark
before heading to the organised chaos that was Isle of Wight and probably the largest single audience of his career
Around half a million people witnessed him struggling with technical problems (the amps picking up radio signals)
exhaustion (the band didn’t actually appear onstage until 2am on Monday 31) and whatever combination of drugs and alcohol he was juggling at the time
Less than 24 hours later they were playing a gig at an amusement park in Stockholm
with Jimi insulting an audience crying out for the hits (“Fuck you
fuck you – come up and play guitar”) and appearing weary with the whole process (“Ah
let me tune my guitar there again – oh
you don’t want to know…”).
The Swedish promoter had allegedly demanded that Hendrix play for no more than an hour so that the audience could use the nearby fun fair
claiming that he’d make more money from the fair than the gig
Justifiably offended – and apparently leaving the stage at one point to argue with the promoter – Jimi got his revenge by playing for 110 minutes
“This song is dedicated to all the girls who get laid,” he said before the final track
all the little girls back there with those little yellow
pink and turquoise panties that they keep throwing on the stage
It’s close to Mother’s Day – anybody that wanna be a mother
the band – billed everywhere as the Jimi Hendrix Experience
something that Hendrix seemed to have given up fighting – travelled to Gothenburg for an outdoor gig
During the day he gave an interview to a Swedish newspaper who asked him about a contribution he had made to ‘the Martin Luther King Memorial Fund’.
“Would you rather I gave it to the Ku Klux Klan?” asked Jimi
“In the USA you have to decide which side you’re on
You’re either a rebel or like Frank Sinatra.” His idealism questioned by the straights
his commitment questioned by his audiences
“I’m tired of lying down and I feel mentally hollowed,” he told the interviewer
If the gig that night was better than the previous one
it still wasn’t enough to impress a visiting Chas Chandler – the man who had managed Hendrix to stardom but parted ways with him the year before.
“He was wrecked,” Chandler said
get into the solo section and then he wouldn’t even remember what song they were playing at the time
It was really awful to watch.”
I’m not sure I’ll live to be 28 years old
I will not be around on this planet any more
unless I have a wife and children – otherwise I’ve got nothing to live for
Billy Cox’s drink was spiked and the drug-free bass player experienced a nightmarish bad trip that
combined with the stress of a busy schedule
over the next few days put him close to a nervous breakdown
The whole camp was at the end of its tether
“I’m not sure I’ll live to be 28 years old,” Jimi told an interviewer the next day
at the moment I feel I have nothing more to give musically
unless I have a wife and children – otherwise I’ve got nothing to live for.”
cutting short his set after only three numbers (he had only ever stopped a gig once before: at the last Band Of Gypsys performance at Madison Square Garden in January that year).
recalled that when she met him earlier that day he was “staggering” and “acting in a funny way”
“I don’t want you to see me like this”
Nefer says that Jimi was unable to even tune his guitar before going onstage
Mitch Mitchell covering his exit with a long drum solo
claimed that “Hendrix collapsed into my arms and we sat him upon a chair
He was cold – cold fever – then they asked for cocaine
Hendrix headed back to his hotel where he spoke once again to Anne Bjorndal
a journalist who had interviewed him earlier.
”I love reading fairy tales,” he told her
“Hans Christian Andersen and Winnie The Pooh
Fairy tales are full of fantasy and they appeal to your imagination.”
Bjorndal claims that Jimi then started crawling around
“Winnie The Pooh is searching,” she quoted him as saying
“It’s winter and the tracks are easy to follow and
Mitch Mitchell got a phone call telling him that his wife had given birth to a baby girl
Mitchell chartered a flight back to London
meeting up with Jimi later that day in Copenhagen for a blistering gig at the city’s KB Hallen hall
Hendrix had spent the day with Nefer at her parents’ house and hit the stage apparently invigorated.
Danish newspaper Politiken raved: ‘Jimi was tired and ill in Arhus
but was so high in Copenhagen that this was true energy
true adrenaline which ran through his fingers
through the guitar and into all of us… As a warrior of love
he stood dressed in many colours and was the best guitarist rock’n’roll music can offer.’
The band then flew on to Berlin to perform at the Super Concert ’70
an indoor festival at the city’s Deutschlandhalle with Procol Harum
Interviewed by American Forces radio before the gig
he was asked if he ever thought there would ever be a festival as successful as Woodstock.
“It’s pretty hard for this sound to get to all those people in such a big crowd
if we had smaller crowds you can really get next to ’em more
you know?” How did he feel about playing in front of 400,000 people
“That’s what I mean,” he said
You know you’re not getting through to all of them…”
By about six we heard this wind and then it turned into a gale
We knew by then there were other problems as well: the usual equipment trouble plus Hell’s Angels with guns..
then caught a train to Grossenbrode in the north
Jimi wanted to lie down so he broke into a locked sleeper car.
“The guard freaked out and stopped the train and threatened to throw us off,” remembered tour manager Gerry Stickells
The situation was smoothed over and the band arrived on Fehmarn on the Saturday afternoon.
“We got there mid-afternoon,” said Mitch Mitchell
“and were supposed to be on at eight
We knew by then there were other problems as well
The usual equipment trouble plus Hell’s Angels with guns.”
Helmut Ferdinand and Timm Sievers had timed their event to coincide with the Isle of Wight festival (with the aim of snagging some major acts
then at the height of his popularity in Germany after his appearance in the Woodstock movie) – but they hadn’t counted on some of the same elements that had disrupted the UK festival to derail theirs: rogue bikers
bad weather and a load of cancellations had soured the ‘Love + Peace’ attitude of the 30,000-strong crowd
“If you think the Isle of Wight was a mess, you should have been to Fehmarn,” comments Ford Crull
Crull was 17 at the time and had heard about Fehmarn while at the Isle Of Wight.
but it was just chaos,” says Crull today
“Sandy Denny kept getting an electric shock from the mic
The whole place was wet and so she kept getting shocks.”
Crull remembers another potentially dangerous experience as he accompanied Rod Stewart and the stage manager over to the business office to collect their payment.
“They just had suitcases packed with cash to give the bands – in American dollars too,” he says
“We had to walk back through everyone with these cases packed with I don’t know how many thousands of dollars
they would have stormed the office.” (That wasn’t the only excess
“They must have had a pound.”)
David Butcher had also been hired as stage hand
“One of the managers of a number of the English bands including Fotheringay
had paid us to be stage hands,” he says
“We were just there and we seemed keen and we spoke English and he said ‘Can you help us out?’ All we had to do was help the roadies and made sure there weren’t too many hangers-on
It was one of those revolving stages so the challenge was
when the guys came up and got on to the backstage bit
they needed peace and quiet and space so they could tune up
We got drinks – anything that was needed
The whole place was wet and so Sandy Denny kept getting shocks
“We were getting paid the equivalent of £12 a day
so this being 1970 we were doing pretty well
this guy who’d employed us appeared in the late afternoon
He had a huge wad of German marks and he said
‘Listen you guys – I’ve got the cash for the bands that have played
I’ve got a couple of bands that are due to play later
but I’m taking them home cos this thing is falling apart
The Angels are just ruining the whole thing
The cash isn’t there – I’m outta here.’
‘Yeah – I’m staying on because of Hendrix.’ He said
that’s up to you – my advice is don’t stay because it’s getting dangerous
Do you want to be stage manager?’ So I said ‘Yes’
and he got out his stage manager pass and stuck it on me
We’d gone from nowhere to getting free press passes
then all of a sudden I was stage manager – whatever that meant.”
Hendrix was due to take the stage at 8pm but when Gerry Stickells visited the site
a force five gale and torrential rain convinced him that it would be a big mistake
Instead Jimi stayed where he was in the Hotel Dania in Puttgarden on the north of the island
Home to most of the musicians appearing at the festival
David Butcher ended up there too: “My memory’s hazy
for good reason – but we landed up in this bedroom and there were people everywhere
Someone had a pair of bongos and there was lots of marijuana going around
I just remember feeling very mellow and Alvin Lee was strumming away and someone was playing bongos and someone was singing – and we just fell asleep where we were.”
Billy Cox wasn’t having nearly as good a time of it
“Billy had kind of a breakdown,” Gerry Stickles told Tony Brown for his 1997 book
The Final Days Of Jimi Hendrix (published by Omnibus
“It was part of my job to nurse him through it
But he was severely paranoid about what was going on
This whole thing was going to collapse and everybody was going to be killed and God knows what else.
"I had to sit on the side of the stage and stuff like that
But this was the last show – ‘let’s just do it
get it over with and get out of here’ – and that’s what happened.”
No sooner had they got there than Stickells was hit on the head by a plank of wood with six inch nails in it
the band posed for German photographer Gernot Piltz
Jimi even rolling around and laughing on the grass backstage.
“Maybe that was before he realised the situation there
Jimi and Mitchell and Cox weren’t even talking to each other
Mitchell’s legs were as thin as my arms.”
It was David Butcher’s job to make sure that the band were taken care of
“I didn’t really pick up on the turmoil that was obviously going on,” says Butcher
He was probably stoned a bit before he arrived
There were one or two joints being passed around
"They had one or two caravans at the back where the stars stayed for the hour or so before they went on
We made sure he was okay and settled in the caravan
then we went back to the stage and made sure the roadies had everything they needed
Later he came out of the caravan and came backstage and then we kept everyone away so that he could tune up and practice.”
Butcher seized the opportunity to introduce himself as social secretary for Keele University and ask Jimi if he’d come and play there
“Sure – talk to Gerry Stickells about it,” said Hendrix
At around one o’clock in the afternoon the Experience took to the stage to boos and jeers and shouts of “Hau ab!” (German for “go home” or “get lost”).
Captured on an ‘official bootleg’ release from Experience Hendrix’s Dagger Records imprint (Live At The Isle Of Fehmarn)
A rare video clip of the festival on YouTube shows Jimi walking to the mic
arms outstretched: “I don’t give a fuck if you boo,” he shrugs
The booing ceases and he then placates them by introducing the band and adding
“We’d like to play some music for you and
Because we’re sorry we couldn’t come on last night
We couldn’t make it together like that
From there, the band launch into Howlin’ Wolf’s Killing Floor
this was the opening song of the Jimi Hendrix Experience’s first ever gig
there was a big cheer and no more boos – the audience are already won over
Then it was Spanish Castle Magic and into All Along The Watchtower
David Butcher was standing at the side of the stage when he was given one more responsibility
“The guy who was controlling the sound took a break
so I was sort of delegated to look after the sound – but hopefully just stand there and not do anything
cos I didn’t understand [how to work the mixing desk]
“He was halfway through All Along The Watchtower when he looked round at me
He’s doing this great solo and then he does that amazing thing where he stops playing with his left hand – he’s just got his right hand on the frets and the solo is magically continuing
y’know – and I’m sort of mesmerised by this when I realise he’s looking at me
He’s walking towards me and he’s saying
trying to find the right fader… It was a wonderful moment because I did actually find the right levers and just moved them up a bit and he kind of smiled and winked
so I obviously did the right thing…”
Umbrellas went up and people huddled under tarpaulins
Jimi laughed and improvised lyrics: “Yeah
bad feeling,” he sang before laughing: “Yeah
the weather is telling you something.”
with a very cold wind,” remembers Butcher
“The rain was coming in and he was standing there
risking being electrocuted but just carrying on
He didn’t move back from the front of the stage
“From my position onstage I could see fights breaking out as Jimi approached the end of his set,” says Butcher
but he was powerless to do anything about it.”
the German police appeared and they basically had a gun fight with the the Hell's Angels
The last two songs Hendrix ever played live were Purple Haze and a suitably stormy version of Voodoo Child (Slight Return)
the final lines of the song – and the final lines that Hendrix would ever sing in public – are as follows: ‘If I don’t see you no more in this world/I’ll meet you in the next one and don’t be late
David Butcher escorted them down the wooden steps at the back of the stage
and they got in a helicopter bound for Hamburg.
Butcher decided it was time for him to leave too
“We weren’t expecting to be paid anything for the final day
All this stuff was on sale – they had guys from Holland out in the crowd
clearly labelled – ‘Whatever you wanna try
I suppose it was on an island and they just thought
By the time we left the Angels were rampaging the stage
He and one of Fotheringay’s roadies commandeered a van and piled the band’s gear inside
“The bikers realised they weren’t gonna get paid and they were running amuck
the German police appeared and they basically had a gun fight with these guys
Our van had the windows smashed and I held up a tarpaulin so he could see while the rains came blasting in
When we got to the hotel where the band was Sandy Denny gave me a big kiss for saving their stuff and they offered me a job
a German anarchist rock band called Ton Steine Scherben took to the stage
Infamous in Germany for songs like Keine Macht Für Niemand (No Power For No One) and Macht Kaputt Was Euch Kaputt Macht (Destroy What Destroys You)
the appearance only added to their infamy: as they played
To some in the audience it looked like Ton Steine Scherben had lit the match
The era of Love + Peace was truly at an end
on September 18 – two months short of his 28th birthday – Jimi Hendrix was dead
David Butcher was “in an agent’s office somewhere in Kensington”
telling him about the conversation he’d had with Jimi about playing at Keele
“This guy was saying how he could liaise with Jimi’s agent and make it happen
And it was at that moment that the door opened and the secretary walked in
If the chaos of the preceding weeks made his death seem almost inevitable
Hendrix wasn’t weary of life – just life in the Experience.
“A lot us hung out at night by the campfires backstage at Isle of Wight,” says Ford Crull
“Jimi and Miles Davis were around one
talking about working together – my friend heard them
Jimi wanted to be taken seriously as a musician
he didn’t want to play the guitar with his teeth… I think his handlers were almost forcing him to cash in
Certainly Hendrix had been optimistic just days before
“Something new has got to come and Jimi Hendrix will be there
I don’t mean three harps and 14 violins
I mean a big band full of competent musicians that I can conduct and write for
And with the music we will paint pictures of earth and space
so that the listener can be taken somewhere…They are getting their minds ready now
getting fat and making themselves ready for the next trip.”
Thanks to David Butcher and Ford Crull
Many of the quotes used in this piece were collected in Tony Brown’s The Last Days Of Jimi Hendrix – thanks to Steve Jackson and Chris Charlesworth of Omnibus Press
Postscript: Famously Jimi jammed with Eric Burdon on the night of his death
playing guitar on a couple of song at Ronnie Scott’s
The Fehmarn festival was his last scheduled performance
Soundgarden's Kim Thayil names the rock and metal bands he believes should be in the Rock and Roll Hall of Fame
and the legendary prog band he can't believe hasn't been inducted already
“I dreamed everything went wrong on stage and we all turned to dust.” Geezer Butler is having nightmares ahead of Black Sabbath's final show
is a mantra for the down-but-not-out generation trying to survive in this burning shitheap of a world
Adapteo Plc Insider information 2 March 2021 at 4:55 p.m
which is responsible for the construction of the Fehmarn Belt tunnel that will link Denmark to the continent
has chosen Adapteo to provide facilities for the extensive FLC Village in Rødbyhavn
The order is the largest in Adapteo’s history
and the company will supply adaptable buildings for accommodation and amenities of a total of 30,000 square meters
The rental period will start in June 2021 and is forecasted to end in 2027
with a total rental value of over EUR 17 million.
The Fehmarn Belt tunnel project will be the world’s longest immersed rail and road tunnel with its 18 kilometres and is currently one of Europe’s most extensive infrastructure projects
The project is expected to create job opportunities for thousands of people
generating a great need for housing and recreation areas for labour connected to the project
Adapteo’s organisation in Denmark will be responsible for delivering and managing an extensive village of adaptable buildings in Rødbyhavn
locker rooms and canteens with a professional kitchen
The village is called FLC village and will contain 30,000 square metres of space
The rental period will start in June 2021 and is forecasted to end in 2027
Adapteo estimates that 30 percent of the total area of 30,000 square meters will be delivered in 2021.
– Being part of this immense infrastructural project that connects parts of Europe
together with being able to secure a flexible way of offering high-quality housing and recreation areas for the people working on the project is
I am also pleased to see that we can expand our new and important worker accommodation customer segment yet further through this project
which is the largest contract in the history of Adapteo
This makes us feel both excited and humbled about the task ahead
is a joint venture in charge of the design and construction of the 18 kilometres immersed tunnel between Denmark and Germany and is constituted by nine international civil works companies which all have individual experience in major infrastructure projects
– Adapteo was chosen for the total solution we were offering and the good layout of our buildings
we have developed and optimised the design to suit all needs for daily use
We are happy with the excellent cooperation throughout the process
Erik Skånsberg, CFO, +46 70 264 70 35, erik.skansberg@adapteo.com
This information is information that Adapteo is obliged to make public pursuant to the EU Market Abuse Regulation
The information was submitted for publication
at 4:55 p.m. CET on 2 March 2021
Adapteo is a leading flexible real estate provider in Northern Europe
rent out and sell adaptable buildings for schools
We know that our society will go through an immense change in the years to come
we believe that adaptability is the best solution
scale up and scale down in a matter of weeks by using a modular and circular building concept
Our buildings can be used for a few days or indefinitely
Adapteo is listed on Nasdaq Stockholm and operates in Sweden
www.adapteogroup.com
Femern Link Contractors (FLC) comprises Aarsleff (Denmark)
VINCI Constructions Grands Projets (France)
Solétanche-Bachy International S.A.S (France)
Wayss & Freytag Ingenieurbau AG (Germany)
By Railway Gazette International2019-02-08T10:26:37
EUROPE: Denmark to Germany rail and road tunnel promoter Femern A/S has formally received a letter providing the Land of Schleswig-Holstein’s approval of the construction plan for the German elements of the project