Romania: Greek utility Public Power Corporation (PPC) Group’s green energy unit will develop a 140 MW wind farm in Romania’s eastern commune of Deleni The project has reached the construction phase and is designed with 23 turbines with an installed capacity of 6.1 MW each It is expected to be connected to the grid by the end of 2025 PPC Group did not disclose the value of the investment The wind farm could generate 370 GWh of green energy annually enough to supply approximately 62000 households It will reduce CO2 emissions by 215000 tonnes annually The completion of the project will bring PPC Renewables’ portfolio in the country to about 850 MW of installed renewable energy sources (RES) capacity The company’s broader objective is to increase the total installed RES capacity in the country to more than 2 GW by the end of 2026 New electricity deal and planned gas pipeline aim to ease Syria’s energy crisis with 400 kV line and 6 million m3 of gas daily from Turkey Christian Bruch visits Baghdad to formalise agreement aimed at potentially adding 14 GW to Iraq’s energy capacity through infrastructure upgrades Xcel Energy will build a 280-km transmission line linking clean energy from southwest Minnesota to over 1 million homes across the Upper Midwest © 2013-2025 | All Rights Reserved MERIT MEDIA INT PPC Renewables started building a 140 MW wind power plant in Romania’s east It said it would complete the facility at the end of next year , 0 PPC is stepping up its expansion in Romania, after acquiring Enel’s entire portfolio in the country last year The state-controlled Greek utility’s green energy subsidiary PPC Renewables declared the start of the construction phase of its 140 MW wind power project in Deleni in Vaslui county The company said it would install 23 GE Vernova turbines of 6.1 MW each in nominal power The wind park near the Romania-Moldova border will be connected to the grid at the end of 2025 It highlighted the region’s rich wind potential and estimated the facility’s annual output at 370 GWh It is equivalent to the electricity needs of 62,000 households PPC Renewables already manages a portfolio of existing projects with a total capacity of over 700 MW in Romania The Greek group claimed its portfolio in the country would exceed 2 GW by the end of 2026 It said it currently runs 4.7 GW in Greece and Romania combined while developing projects for another 20 GW. The power utility intends to get all of it online by 2030 In addition to large photovoltaic and wind projects, PPC Renewables invests in hydropower including pumped storage, in geothermal energy, the biomass and biogas segment and battery energy storage. Be the first one to comment on this article 02 May 2025 - The project is located in Constanța county recognized for its superior yields in green energy production 02 May 2025 - The Sunčana (Sunny) Vipava project envisages installing solar power plants with a combined capacity of 20 MW 30 April 2025 - OMV put into operation its 10 MW green hydrogen plant at the Schwechat refinery 30 April 2025 - It is the second time this year that MVM contracted gas-fueled and hydrogen-ready power plants at sites of former fossil fuel facilities © CENTER FOR PROMOTION OF SUSTAINABLE DEVELOPMENT 2008-2020 website developed by ogitive PPC Renewables is building a 140 MW wind farm and Eurowind Energy is installing the first turbines at the Pecineaga location in Romania 0 PPC Renewables Romania marked the start of construction of its Deleni facility in Vaslui county in the country’s northwest The 140 MW wind power plant will consist of 23 turbines of 6.1 MW each Deleni is the first major project of the kind in the Western Moldavia or Moldova region It will attract other projects to the area according to Minister of Energy Sebastian Burduja “And for the national energy system it means a strategic diversification of wind energy production considering that until now the important parks are concentrated in the Dobrogea area Congratulations to the PPC company for taking on this major and courageous project,” he said Burduja: By actually locating the consumption closer to the place of production for electricity you will be able to offer a more competitive electricity price Municipal budgets will be doubled with the new tax income The turbines will be on the territories of the communes Deleni with a 400/200/100 kV substation in nearby Banca “This green energy means the future of tomorrow’s generations it means energy production at a competitive price so cheaper energy for Romanians and for the private sector It means the chance for this area to have higher taxes and fees to create jobs and have an additional factor for attracting investors By actually locating the consumption closer to the place of production for electricity you will be able to offer a more competitive electricity price,” Burduja pointed out PPC Renewables Romania estimated the annual output at 370 GWh The minister invited the company to participate at the upcoming auction for support under contracts for difference (CfDs) Including Deleni, the firm’s renewable energy capacity reaches 1.5 GW. In August, it bought the 600 MW Fântânele-Cogealac-Gradina onshore wind park PPC Renewables Romania is a subsidiary of Greece’s government controlled Public Power Corp The PPC Renewables branch has 4.7 GW altogether in the two countries In Romania it aims to surpass 2 GW by the end of 2026 Danish developer and operator of wind, photovoltaic and hybrid projects Eurowind Energy said the construction of its Pecineaga wind farm is progressing. It is in Constanța county in Dobrogea or Dobruja province in the country’s east Installation started of the Siemens Gamesa turbines SG 6.6-170 The facility will consist of eight machines totaling 48 MW and generate an estimated 176 GWh per year The company expects the start of operation in the first quarter Eurowind Energy entered the Romanian market in 2011 Among other recent developments in wind energy, Rezolv Energy signed a string of virtual power purchase agreements (VPPAs) for its Vifor wind power project in the country’s east. Nala Renewables secured EUR 214 million to acquire and build a 99.2 MW wind farm Earlier this year, Rezolv Energy also signed the grid connection agreement for a 600 MW wind project in Romania, while wpd advanced a 528 MW wind farm in Suceava county PPC Renewables Romania has started the construction works of the Deleni wind farm which will become the largest renewable energy production plant located in Moldova region “This park in Vaslui County marks an important step for the development of the energy sector in the Moldavian region It is the first major project of its kind in the region and will bring major benefits for the local community and our energy security affordable and clean energy – this is the future such an investment will attract other projects to the area it means a strategic diversification of wind energy production given that so far the major wind farms are concentrated in the Dobrogea area Congratulations to PPC for taking on this major and courageous project We encourage investors in the energy sector to also target the Moldovan area in their investment plans,” said Sebastian Burduja “This will be the second wind power plant of PPC Renewables outside the Dobrogea area the one in which the production of electricity in wind power plants has been concentrated so far The wind potential of this area is important and the geographical diversification will help both to improve Romania’s energy mix and to reduce the shortage of energy production capacities in the North of the country We are glad to be able to contribute to the development of a clean energy sector in Romania which will help the economic competitiveness of the country and local communities” which is scheduled to be connected to the grid by the end of 2025 will be equipped with 23 GE Vernova turbines The power of the turbines is almost three times higher than that of the turbines installed in the previous stage of massive wind energy development in Romania The park will generate approximately 370 GWh of electricity annually avoiding CO2 emissions of about 215,000 tons annually and providing enough energy to power the equivalent of 62,000 households the equivalent of a city the size of Vaslui The wind turbines will be installed in the administrative areas of the localities of Deleni Bogdănești while the transformer station for interconnection 400/220/110 kV is in Banca The infrastructure in the area will allow the inhabitants access to the connecting roads that pass through the park It will have three primary substations; the one from Banca will be the interconnection station with the National Energy System The wind project also allows the addition of energy storage capacities PPC Renewables Romania’s total installed renewable energy capacity will reach approximately 1.5 GW PPC Group’s plan is to exceed the level of 2 GW of renewable energy production units in Romania by the end of 2026 With a total installed capacity of 4.7 GW in Greece and Romania PPC Renewables continues to be the leading electricity supplier in South-Eastern Europe with a portfolio of 20 GW planned until 2030 and beyond (PPC) is the leading utilities in the energy sector in South-Eastern Europe operation of networks and sale of advanced energy products and services in Greece PPC has a total installed capacity of 11.5 GW hydro and renewable sources with a total annual production of over 21 TWh with a currently installed capacity of 700 MW from wind and photovoltaic power plants and continues at a fast pace to strengthen its portfolio through large-scale projects,  in line with the objective of becoming the largest player in the renewable energy market in Romania Silky Redcliffe Dolphins centre Deleni Paitai helped her team secure the two points in Round 5 of the Harvey Norman Under 19s Harvey Norman Under 19 grand final highlights: Tigers v Cutters UPDATE: Brisbane Tigers centre Relna Hosea has taken out this year's weapon vote The talent of the Harvey Norman Under 19 competition has shone this season there are many athletes and performances to be proud of from the seven weeks of the regular season one player was highlighted as the "weapon" of the round highlighting the athletes of the Harvey Norman Under 19 as attention turns towards the upcoming finals series it is time for the fans to decide which player deserves the title of "weapon of the year" with the winner to be announced the following day on Tuesday The nominees - based off the weekly winners - are below The gun centre kickstarted her Harvey Norman Under 19 season in style running in a hat-trick against the Redcliffe Dolphins in Round 1 Hosea - who is heading into the Harvey Norman Under 19 finals off the back of a successful Women's National Championships campaign with the Queensland Sapphires - also amassed 159 run metres in Round 1 and registered three tackle breaks and three line breaks Redcliffe forward Hicks - who can play in the front row and second row - was key for the Dolphins hitting back in Round 2 for their first win of the season In claiming the 26-20 victory over Burleigh a barnstorming Hicks scored a try and set up another The finals-bound Brisbane Tigers were one of the strongest performing teams all season In Round 3 they smashed past the Souths Logan Magpies with a 40-10 win and Elika was a standout in this effort The destructive lock was hard to contain and bagged a double in her side's victory Crafty little hooker Masun-Feleti was unstoppable in Round 4 Not only did she rack up a hat-trick against the Wide Bay Bulls but she ran a stunning 143 metres and recorded eight tackle breaks and three line breaks in an attacking masterclass What a weapon: Vaitafao-Gisele Masun-Feleti In Redcliffe's 32-18 Round 5 victory over the Souths Logan Magpies silky centre Deleni Paitai was a sensation Destructive forward Dunn has been a key part of the Clydesdales' finals push this year with the towering prop putting in a stunning 39-minute performance Dunn scored a try and recorded five tackle breaks Little Mackay dynamo Lawson is another who has contributed greatly to her side's finals push The playmaker finished the 2024 regular season strongly making a great impact for her team in their 36-4 win over Central Queensland Present everywhere on the field and aiming up in defence Catch all the Harvey Norman Under 19 finals action from Saturday, April 6, by subscribing to Qplus.tv. Semi-Finals: Weekend Preview - Mal Meninga Cup Mackay and Cairns women eager to dethrone favourites Townsville in Foley Shield Rezolv Energy has signed a joint grid connection agreement for its Dunarea East and West wind power projects in Constanța county 0 Right after important updates on one of the biggest solar power investments in Bulgaria and the Dama Solar photovoltaic project in Romania of over 1 GW Rezolv Energy said it made substantial progress with a 600 MW wind power project in southeastern Romania The Prague-based renewables developer said it has signed the grid connection agreement for Dunarea East and West. Both wind farms would have the same connection point. Therefore the joint facility would match the nearby Fântânele-Cogealac wind power plant which, at 600 MW, is the biggest in Europe in the onshore segment Rezolv is developing Dunarea East and West in partnership with Low Carbon The locations are in the communes of Adamclisi and Deleni on flat terrain The project requires a 400 kV substation to feed the output into the transmission network Dunarea East and West are located in Adamclisi and Deleni in southeastern Romania The wind park is scheduled to gradually come online starting in 2026 The company revealed it would sell power to commercial and industrial users through long-term power purchase agreements (PPAs) “Along with the positive impact on the local communities Dunarea East & West will generate a huge amount of clean power for corporate off-takers offering companies long-term price stability and peace of mind over the security of supply – as well as an emissions reduction guarantee,” General Manager for Romania Marian Pavel stated Rezolv said it has more than 2 GW in renewable energy capacity ready for construction in South Eastern Europe be the largest solar power plant in Europe at this moment The company also has the 450 MW Vifor wind project in Buzău county It recently obtained regulatory clearance for St a future 229 MW photovoltaic park in northeastern Bulgaria The financing is intended for two photovoltaic projects in Giurgiu county in the south The company’s subsidiary RTG Solar Energy is developing the Iepurești project of 169 MW The Ghimpați solar power plant is formally under special purpose vehicle Solis Imperium Motivated by legal reforms and the European Union’s funding, renewable energy projects have flooded Romania over the last few years and numerous utility-scale units have lately been coming online The government has adopted the draft offshore wind power bill in December institutions and firms – accounted for 1.1 GW It puts the category at the forefront of the energy transition and decarbonization in Romania 05 May 2025 - The delegations from the two countries met on the sidelines of the 10th summit meeting of the Three Seas Initiative 05 May 2025 - The Trebinje 3 photovoltaic plant would have an installed capacity of 53.63 MW and an estimated annual production of 85.5 GWh 05 May 2025 - VDE Renewables found that SolarEdge’s advanced safety capabilities minimize photovoltaic system risks and effectively prevent fire hazards Tisíce lidí se ve Varšavě zúčastnily Pochodu nezávislosti výročí samostatnosti Polska pořádala krajní pravice Kvůli pandemii se plánoval pouze automobilový průvod Policie je nechala i přes zákaz starosty jít kdy radikální část účastníků napadla její příslušníky „Asi po patnácti minutách nejspíš fotbaloví chuligáni napadli těžkooděnce pyrotechnikou a kameny,“ popsal z Varšavy zpravodaj ČT Lukáš Mathé Několik lidí podle něj při potyčkách utrpělo zranění Policie zasahovala slzným plynem či gumovými projektily na kterém visely dvě vlajky: jedna duhová symbolizující snahu o rovnoprávnost sexuálních menšin a druhá se symbolem blesku který si vzaly do znaku ženy protestující proti nedávnému rozhodnutí Ústavního soudu fakticky zakazujícímu potraty Radikální pravice dlouhodobě brání možnostem sexuálních menšin zakládat například rodinu a má také blízko k církevní interpretaci práva na život od početí Hlavní část pochodu skončila u Národního stadionu Někteří Poláci oslavili výročí obnovení nezávislosti země automobilovou jízdou listopadu připomíná opětovné získání nezávislosti které se dočkalo po 123 letech v roce 1918 Polské království patřívalo k velkým evropským státům ale v letech 1772 až 1795 při takzvaném trojím dělení zaniklo Loni se varšavského pochodu zúčastnilo několik desítek tisíc lidí a pořádkové síly bránily střetům mezi nacionalisty a účastníky levicové protidemonstrace Při předloňských oslavách stého výročí obnovení nezávislosti šli představitelé vlády a prezident Andrzej Duda poprvé ve stejném průvodu jako přívrženci radikální pravice Akce se tehdy zúčastnilo na 200 tisíc lidí is added to the development of the RES portfolio of PPC Renewables The new wind plant is designed with 23 GE Vernova 6.1 MW turbines and will be connected to the grid by the end of 2025 Given the high wind potential of the region the estimated annual generation of the power plant is expected to be 370 GWh per year CO2 emissions of 215,000 tons will be avoided annually the project is expected to provide enough energy to power the equivalent of approximately 62.000 households PPC Renewables operates in Romania an existing portfolio of more than 700MW the total installed RES capacity of the PPC Group in the country will reach approximately 850MW PPC Group has currently a total installed RES capacity of 4.7GW both in Greece and Romania being the leading Southeast European electric utility with a strong pipeline of 20GW invests in the power of nature to promote green electricity generation and energy storage projects in addition to the large photovoltaic and wind farms it builds innovates in Southeast Europe with its activities in all forms of renewable energy Gun Brisbane Tigers centre Relna Hosea kickstarted her Harvey Norman Under 19 season in style